History
  • No items yet
midpage
Campbell v. George J. Igel & Co., Inc.
3 N.E.3d 219
Ohio Ct. App.
2013
Read the full case

Background

  • William M. Campbell (landowner) signed a preprinted Construction Site Agreement with George J. Igel & Co., Inc. (contractor) on June 20, 2011, granting the contractor permission to use his property as a staging area for an ODOT road project.
  • The Agreement required the contractor to perform site work (embankment, topsoil replacement, grading/seed, drainage, aggregate) and included a "Lump Sum Payment $50,000.00" provision: $25,000 "at start" and $25,000 "upon completion and acceptance."
  • Contractor won the ODOT project bid but chose not to use or disturb Campbell's property; it instead used state property and paid Campbell nothing.
  • Campbell sued for breach of contract seeking $50,000. The trial court converted a pleading challenge to summary judgment, denied Campbell's summary-judgment motion, and granted the contractor's summary judgment, finding payment was conditioned on actual use of the property.
  • The appellate court reviewed de novo, held the Agreement unambiguous and that the payment obligation was not conditioned on actual use of the property, reversed summary judgment for the contractor, and remanded for a damages hearing.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the contractor's $50,000 payment obligation was conditioned on actual use of Campbell's property Campbell: Payment was an unconditional exchange for making the property available; "at start" and "upon completion" speak only to timing Igel: Agreement used "permission" and payment timing language to create a condition precedent — payment due only if property was used Court: Payment was an unconditional contractual promise; use was not a condition precedent
Whether parol evidence may show a condition precedent Campbell: Written agreement is integrated and unambiguous; parol evidence inadmissible Igel: Surrounding circumstances (no bid yet) justify parol evidence to show contingency Court: Integration clause and clear written terms bar parol evidence to create a condition inconsistent with the writing
Whether plaintiff satisfied elements of breach of contract Campbell: Performed by making property available; contractor failed to pay Igel: Contractor argues no obligation arose absent use Court: Contract existed; Campbell performed; contractor breached; material facts remain on damages
Appropriateness of summary judgment for damages Campbell: Sought summary judgment on breach and damages Igel: Opposed liability and damages Court: Reversed contractor's summary judgment on liability; denied Campbell's summary judgment on damages and remanded for damages determination

Key Cases Cited

  • Smith v. McBride, 130 Ohio St.3d 51, 955 N.E.2d 954 (Ohio 2011) (summary-judgment review standard and de novo review)
  • Dresher v. Burt, 75 Ohio St.3d 280, 662 N.E.2d 264 (Ohio 1996) (party moving for summary judgment bears initial burden; nonmoving party must then show genuine issue)
  • Doner v. Snapp, 98 Ohio App.3d 597, 649 N.E.2d 42 (Ohio Ct. App. 1994) (elements of breach of contract claim)
  • National City Bank of Cleveland v. Erskine & Sons, 158 Ohio St. 450, 110 N.E.2d 598 (Ohio 1953) (definition of breach as failure without legal excuse)
  • Luntz v. Stern, 135 Ohio St. 225, 20 N.E.2d 241 (Ohio 1939) (when undisputed facts present, performance vs. breach of written contract is a question of law)
Read the full case

Case Details

Case Name: Campbell v. George J. Igel & Co., Inc.
Court Name: Ohio Court of Appeals
Date Published: Aug 14, 2013
Citation: 3 N.E.3d 219
Docket Number: 13CA4
Court Abbreviation: Ohio Ct. App.