History
  • No items yet
midpage
905 F.3d 537
7th Cir.
2018
Read the full case

Background

  • Richard Griff began as a locomotive engineer, was later promoted to supervisory/managerial roles, and elected to retain engineer seniority under Article 9 by continuing union dues.
  • Union Pacific fired Griff in February 2013 for falsifying safety and training documentation; the railroad treated managerial positions as outside the collective-bargaining discipline rule that guarantees a predeprivation hearing for "locomotive engineers."
  • Union Pacific refused to allow Griff to exercise his seniority post-termination; Griff and the Brotherhood argued Article 9 permitted post-termination return to engineer status and therefore entitled him to the pretermination hearing in the discipline rule.
  • The Brotherhood submitted the grievance to the National Railroad Adjustment Board (First Division); the Board concluded managers cannot exercise seniority after termination for cause, but required the carrier to have a good-faith basis to fire a manager who retained Article 9 rights; the Board found Union Pacific met that standard and denied relief.
  • The Brotherhood sued in federal court challenging the Board’s award on jurisdictional, Railway Labor Act, and due-process grounds; the district court granted summary judgment for Union Pacific.
  • The Seventh Circuit affirmed, rejecting all challenges and awarding Rule 38 sanctions to Union Pacific for a frivolous appeal; Union Pacific to submit costs and fees.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Board jurisdiction to decide whether Griff was an "engineer" Board lacked authority to conclude Griff was not an engineer because its jurisdiction covers disputes "involving" engineers only Board had jurisdiction because Griff claimed engineer status under the CBA, thus triggering the Board to decide application of contract terms to him Board had jurisdiction; it may resolve disputes that determine whether a claimant falls within covered categories
Board’s imposition of a good-faith requirement on employer Board exceeded jurisdiction by regulating supervisors outside its scope Board applied the CBA to decide whether a disputed beneficiary (Griff) had rights; that is within its remit Board acted within jurisdiction in applying the CBA and requiring a good-faith basis where Article 9 granted potential rights
Due process: insufficiency of evidence for good-faith finding Board lacked evidentiary basis to accept Union Pacific’s stated reason in good faith; thus hearing required Union Pacific presented its reason; Brotherhood did not dispute the factual basis before the Board and raised pure contract law issues No due-process violation: arbitral due process is relaxed, evidence presented and not contested, so Board reasonably accepted carrier’s good-faith explanation
Railway Labor Act / "usual manner" requirement Board violated §153 First(i) by not remanding to carrier for the usual-manner (on-property) investigation on the good-faith question "Usual manner" governs carrier procedures, not the Board; Board may interpret CBA and resolve disputes after usual-manner efforts fail No RLA violation: "usual manner" applies to carrier-level procedures; the Board properly interpreted the CBA and denied a hearing under its terms
Rule 38 sanctions (implicit) appeal was non-frivolous Appeal was frivolous: arguments contradicted clear precedent and the Board’s opinion Sanctions granted; Union Pacific to submit accounting for fees and costs

Key Cases Cited

  • Union Pac. R.R. Co. v. Sheehan, 439 U.S. 89 (arbitral award may be set aside only on narrow statutory grounds)
  • Hill v. Norfolk & W. Ry. Co., 814 F.2d 1192 (7th Cir.) (private carrier action not a Fifth Amendment violation)
  • Tice v. Am. Airlines, Inc., 288 F.3d 313 (7th Cir.) (Adjustment Boards have exclusive jurisdiction over CBA disputes in railroad/airline industries)
  • United Steelworkers of Am. v. Warrior & Gulf Nav. Co., 363 U.S. 574 (arbitrators may look to industry practices when interpreting CBAs)
  • Int’l Bhd. of Elec. Workers v. CSX Transp., Inc., 446 F.3d 714 (7th Cir.) (arbitral due-process standards are relaxed; adequate notice, hearing, impartial decision required)
  • Ryan v. Union Pac. R.R. Co., 286 F.3d 456 (7th Cir.) ("usual manner" under §153 First(i) refers to carrier procedures, not Board process)
  • Arnold v. Villarreal, 853 F.3d 384 (7th Cir.) (Rule 38 frivolous-appeal standard)
Read the full case

Case Details

Case Name: Brotherhood of Locomotive Eng v. Union Pacific Railroad Compan
Court Name: Court of Appeals for the Seventh Circuit
Date Published: Sep 25, 2018
Citations: 905 F.3d 537; 17-1897
Docket Number: 17-1897
Court Abbreviation: 7th Cir.
Log In
    Brotherhood of Locomotive Eng v. Union Pacific Railroad Compan, 905 F.3d 537