History
  • No items yet
midpage
2021 Ohio 1813
Ohio Ct. App.
2021
Read the full case

Background

  • Pompili (subcontractor) supplied precast concrete under a chain of subcontracting for a university project and recorded a mechanic’s lien after Masonry (its direct subcontractor) failed to pay several invoices.
  • Masonry obtained a release-of-lien bond from Western Surety and the trial court approved the bond and ordered the lien released.
  • Pompili sued Masonry, Western Surety, and others; claims remaining at trial included breach of contract and Prompt Payment Act claims against Masonry and a claim against Western Surety on the lien bond.
  • The trial court tried the case, awarded Pompili damages, interest, and attorney fees against Masonry, but the judgment was silent as to Pompili’s claim against Western Surety; the court included Civ.R. 54(B) language.
  • Masonry appealed; the appellate court sua sponte questioned final appealability because Pompili’s unresolved claim against Western Surety raised interrelated factual/legal issues (Western Surety asserted Pompili’s defective performance defense).
  • The court held it lacked jurisdiction because the judgment was not a final appealable order and dismissed the appeal; later proceedings included a trial-court ruling finding Western Surety obligated, and that ruling was also appealed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Final appealability of the trial-court judgment Pompili: Civ.R. 54(B) language makes the order final and appealable Masonry: same — the order is final and appealable Not final; Civ.R. 54(B) language alone insufficient because unresolved related claims remain
Whether Pompili’s claim against Western Surety is interrelated with claims resolved against Masonry Pompili: claim against surety is separate Western Surety: claim interrelates because it defends liability based on Pompili’s defective performance Interrelated — unresolved surety claim involves same facts and legal issues, so it prevents finality
Effect of Civ.R. 54(B) certification Pompili: certification renders the partial judgment immediately appealable Opposing position: certification cannot convert a nonfinal order into a final one when unresolved related claims remain Court: Civ.R. 54(B) is not a "mystical incantation"; order must be final before 54(B) makes it appealable (citing controlling Ohio precedent)
Appellate court’s duty to examine jurisdiction sua sponte Pompili: (implicit) appellate review should proceed Masonry: (implicit) proceed with appeal Court: duty to examine final-appealable-order; because order not final, appeal dismissed for lack of jurisdiction

Key Cases Cited

  • Wisintainer v. Elcen Power Strut Co., 67 Ohio St.3d 352 (1993) (Civ.R. 54(B) language does not by itself make a nonfinal order appealable)
  • Chef Italiano Corp. v. Kent State Univ., 44 Ohio St.3d 86 (1989) (discussing final-order requirements and limits of Civ.R. 54(B))
  • Gen. Acc. Ins. Co. v. Ins. Co. of N.Am., 44 Ohio St.3d 17 (1989) (Civ.R. 54(B) cannot alter the requirement that an order be final before 54(B) renders it appealable)
  • Sullivan v. Anderson Twp., 122 Ohio St.3d 83 (2009) (explaining that Civ.R. 54(B) certification is for efficiency and to avoid piecemeal appeals, but does not eliminate finality requirements)
Read the full case

Case Details

Case Name: Broadway Concrete Invests., L.L.C. v. Masonry Contracting Corp.
Court Name: Ohio Court of Appeals
Date Published: May 27, 2021
Citations: 2021 Ohio 1813; 109839
Docket Number: 109839
Court Abbreviation: Ohio Ct. App.
Log In
    Broadway Concrete Invests., L.L.C. v. Masonry Contracting Corp., 2021 Ohio 1813