History
  • No items yet
midpage
925 N.W.2d 94
Neb. Ct. App.
2019
Read the full case

Background

  • Charles and Sylvia Bridwell contracted with Brett and Gary Walton (Walton Contracting) to build a home addition; original bid ≈ $32,182, expanded to $63,207.46 for interior finish.
  • Work ran from Sept 2013 to June 2014; Bridwells paid $50,400 but raised multiple defects during construction and provided a signed punch list.
  • On June 3, 2014, after a disputed conversation, Walton Contracting packed up and left the site before completion.
  • Bridwells sued for breach of contract alleging nonworkmanlike construction; Waltons counterclaimed for unpaid work.
  • At trial, testimony included contractor estimates (≈ $99,400–$120,014) to demolish and rebuild versus lower figures for piecemeal repairs; jury awarded Bridwells $40,000 and found for Bridwells on the counterclaim.
  • District court denied Waltons’ motions to amend pleadings (to add failure-to-mitigate defense), to dismiss for lack of evidence of the workmanlike standard, and for new trial/remittitur; appeal followed.

Issues

Issue Plaintiff's Argument (Bridwell) Defendant's Argument (Walton) Held
Motion to amend pleadings to add failure-to-mitigate (mold/water) Amendment unnecessary; defense waived and not pled Evidence at trial raised mold/water issues implicitly so amendment to conform to evidence should be allowed Denied — failure to mitigate is an affirmative defense that must be pled; evidence insufficient to justify amendment and defense was waived
Dismissal for failure to prove standard of workmanlike manner Bridwells presented expert/contractor testimony showing defects and repair costs Waltons argued Bridwells failed to establish the applicable standard so prima facie case lacking Motion treated as directed verdict; Waltons waived error by introducing evidence after denial and by not renewing motion — dismissal denied
New trial / remittitur for passion/prejudice and excessiveness Verdict influenced by speculative mold/demolition testimony and was excessive compared to itemized repair costs Jury award inconsistent with contractor demolition estimates and lower than full demolition bids; not shockingly high Denied — award ($40,000) was below contractor demolition estimates and not so large as to shock conscience or be clearly excessive
Verdict unsupported / quotient verdict claim Bridwells contend verdict supported by testimony and estimates Waltons claim verdict was a quotient or unsupported by evidence Denied — sufficient evidence supported the verdict; no record evidence of an agreement to be bound by a quotient verdict

Key Cases Cited

  • United Gen. Title Ins. Co. v. Malone, 289 Neb. 1006 (discretionary standard for amending pleadings)
  • Smith v. Colo. Organ Recovery Sys., 269 Neb. 578 (standard for upholding jury verdicts)
  • Maricle v. Spiegel, 213 Neb. 223 (failure to mitigate is an affirmative defense that must be pled)
  • Estermann v. Bose, 296 Neb. 228 (pleading rules modeled on federal rules; affirmative defenses guidance)
  • Palmtag v. Gartner Constr. Co., 245 Neb. 405 (motion to dismiss for failure to prove prima facie case treated as directed verdict)
  • Anis v. BryanLGH Health System, 14 Neb. App. 372 (quotient verdict definition and invalidity principles)
  • Barbour v. Jenson Commercial Distributing Co., 212 Neb. 512 (remittitur for excess verdicts where illegal portion distinguishable)
  • Crewdson v. Burlington Northern RR. Co., 234 Neb. 631 (verdict shocks conscience test for passion or prejudice)
  • Chafin v. Wisconsin Province Society of Jesus, 301 Neb. 94 (assignment-and-argument requirement for appellate review)
Read the full case

Case Details

Case Name: Bridwell v. Walton
Court Name: Nebraska Court of Appeals
Date Published: Mar 12, 2019
Citations: 925 N.W.2d 94; 27 Neb. Ct. App. 1; 27 Neb. App. 1; A-17-1011
Docket Number: A-17-1011
Court Abbreviation: Neb. Ct. App.
Log In