History
  • No items yet
midpage
Bridgeport Harbour Place I, LLC v. Ganim
131 Conn. App. 99
| Conn. App. Ct. | 2011
Read the full case

Background

  • Steel Point redevelopment in Bridgeport; development agreement among Bridgeport, plaintiff, and United Illuminating; multiple amendments and a planned restated/restated land disposition agreement; city terminated the development agreement around 2000; plaintiff claimed damages including lost profits and overhead and alleged bribery/corruption by defendants; jury returned partial verdict awarding damages to plaintiff and punitive damages later awarded to plaintiff against Lenoci and Ganim.
  • Plaintiff alleged defendants acted to oust it as developer in favor of United Properties, including bribery schemes involving Ganim and Lenoci defendants.
  • Development approvals were discretionary political acts not guaranteed, causing uncertainty in whether lost profits could be proven.
  • Court denied damages for lost profits and overhead as speculative, and limited evidence of prior misconduct; awarded punitive damages under CUTPA against Lenoci and Ganim but after balancing factors.
  • Cross-appeals: defendants challenged collateral estoppel and statute of limitations defenses; court held RICO standards differ from common-law proximate cause, saved claims under accidental failure of suit; affirmed overall judgment.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether lost profits evidence was admissible Lost profits were recoverable if causation shown Damages speculative; no certain contract Preclusion proper; lost profits not proven with reasonable certainty
Whether overhead damages were admissible Overhead costs are recoverable in tort/contract Overhead not established; discovery flaws Overhead evidence properly precluded
Whether evidence of prior misconduct on Kasper’s part was admissible Evidence relevant to conspiratorial knowledge Evidence outside pleadings; limited by 4-5; not integral to claim Court did not abuse discretion; evidence excluded as not an integral part of the plan to interfere with contract
Whether punitive damages were properly calculated under CUTPA against Lenoci and Ganim Should be high punitive damages given wealth and conduct Should be limited; ratio constrained by due process Six times actual damages awarded; not an abuse of discretion
Whether plaintiff's state claims were barred by collateral estoppel or statute of limitations Claims not barred; 52-592 saves claims Collateral estoppel and limitations apply Collateral estoppel did not bar state claims; 52-592 savings applied; judgment affirmed

Key Cases Cited

  • Beverly Hills Concepts, Inc. v. Schatz & Schatz, Ribicoff & Kotkin, 247 Conn. 48 (Conn. 1998) (damages for lost profits must be proven with reasonable certainty)
  • Goodstein Construction Corp. v. City of New York, 80 N.Y.2d 366 (N.Y. 1992) (lost profits from a prospective land development contract may be speculative)
  • State v. Randolph, 284 Conn. 328 (Conn. 2007) (common plan/scheme exceptions to 4-5(b) admissibility limited; narrow standard)
  • Holmes v. Securities Investor Protection Corp., 503 U.S. 258 (S. Ct. 1992) (RICO proximate cause requires more than but-for; proximate cause limits standing)
  • Lerner v. Fleet Bank, N.A., 459 F.3d 273 (2d Cir. 2006) (RICO proximate cause doctrine differs from common-law proximate cause; standing issues distinct)
  • Abrahams v. Young & Rubicam, Inc., 79 F.3d 234 (2d Cir. 1996) (statutory/causation interplay in proximate cause analysis)
  • Exxon Shipping Co. v. Baker, 554 U.S. 471 (S. Ct. 2008) (guidance on punitive damages, deterrence, and due process considerations)
  • State Farm Mut. Auto. Ins. Co. v. Campbell, 538 U.S. 408 (S. Ct. 2003) (three guideposts for evaluating punitive damages under due process)
Read the full case

Case Details

Case Name: Bridgeport Harbour Place I, LLC v. Ganim
Court Name: Connecticut Appellate Court
Date Published: Aug 30, 2011
Citation: 131 Conn. App. 99
Docket Number: AC 30549
Court Abbreviation: Conn. App. Ct.