History
  • No items yet
midpage
BRC Rubber & Plastics, Inc. v. Continental Carbon Co.
949 F. Supp. 2d 862
N.D. Ind.
2013
Read the full case

Background

  • BRC Rubber & Plastics, Inc. and Continental Carbon Company entered a January 1, 2010 supply contract for all of BRC’s carbon black needs (N339, N550, N762) over five years.
  • The agreement contemplated annual purchases around 1.8 million pounds and allowed rebates/penalties for volumes outside a defined range, with forecasts used for planning but not reserved production.
  • In 2010 Continental supplied more than the estimated amount and granted a modest rebate; BRC’s requirements rose with automotive demand in 2011.
  • In April 2011 Continental sought a price increase and began restricting shipments, subsequently downgrading BRC’s customer tier, and failing to confirm several purchase orders from BRC.
  • BRC demanded adequate assurance of performance under UCC § 2-609; Continental failed to confirm/shipment and proposed price increases, prompting BRC to cover with alternative suppliers.
  • BRC terminated the agreement on June 2, 2011 and filed suit; Continental later delivered additional shipments but the parties could not settle, and BRC stopped ordering in September 2011.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether BRC’s April 26 orders were placed in good faith BRC acted in good faith under the contract terms. BRC’s increases were not in good faith or were unreasonably disproportionate. BRC acted in good faith.
Whether the April 26 order was unreasonably disproportionate to the stated estimate Orders were within the contract’s 1.8 million pound baseline and forecasted variability; not unreasonably disproportionate. The May/June increases exceeded the stated estimate and were unreasonably large. Not unreasonably disproportionate as a matter of law.
Whether Continental repudiated the contract by failing to provide adequate assurance and by limiting supply to 1.8 million pounds Continental failed to provide adequate assurance and signaled performance limited to 1.8 million pounds, constituting repudiation. Continental’s statements were interpretations of the contract, not a repudiation. Continental repudiated the contract; BRC could terminate and seek damages.
Whether Continental's defense of commercial impracticability bars recovery No; the shortage was not unforeseeable or beyond contemplation, and allocations were not fair. Maintenance outages and demand increases were a basis for impracticability. Commercial impracticability defense fails; no excuse for breach.

Key Cases Cited

  • Empire Gas Corp. v. Am. Bakeries Co., 840 F.2d 1333 (7th Cir.1988) (good faith variations allowed in requirements contracts)
  • Ind.-Am. Water Co. v. Town of Seelyville, 698 N.E.2d 1255 (Ind. Ct. App.1998) (good faith standard for variations in requirements contracts)
  • Westmoreland v. Colo. Westmoreland, 667 F. Supp. 636 (N.D. Ind.1987) (variance from estimated requirements evaluated for reasonableness)
  • Orange & Rockland Utils., Inc. v. Amerada Hess Corp., 59 A.D.2d 110 (N.Y. App. Div.1977) (no rigid definition for 'unreasonably disproportionate' quantity)
  • Lenape Res. Corp. v. Tenn. Gas Pipeline Co., 925 S.W.2d 565 (Tex.1996) (reasonableness of demand fluctuations in contract performance)
  • Eden United, Inc. v. Short, 573 N.E.2d 920 (Ind.Ct.App.1991) (anticipatory repudiation requires clear intent not to perform under contract interpretation)
Read the full case

Case Details

Case Name: BRC Rubber & Plastics, Inc. v. Continental Carbon Co.
Court Name: District Court, N.D. Indiana
Date Published: Jun 5, 2013
Citation: 949 F. Supp. 2d 862
Docket Number: Cause No. 1:11-CV-190
Court Abbreviation: N.D. Ind.