midpage
Sign in to see your projects.
91 A.3d 830
R.I.
2014
Read the full case

Background

  • Berkshire (general contractor) and Bilray (subcontractor) disputed work on a Bristol, RI project after Berkshire terminated Bilray in April 2010; the parties agreed to binding arbitration.
  • Bilray sought the contract balance (~$112,240) and payment for additional work; Berkshire asserted Bilray had executed a March 25, 2010 release waiving claims for labor/materials/work through that date.
  • The release contained provisions (paras. 3–5) waiving claims and indemnifying the owner; a referenced requisition was not in the record.
  • The arbitrator concluded the release did not clearly extinguish Bilray’s claims (partly because the requisition wasn’t produced), held Berkshire’s termination wrongful, and awarded Bilray a net sum.
  • Berkshire moved in Superior Court to vacate under § 10-3-12, arguing the arbitrator manifestly disregarded Max Fish and the plain release language; the trial justice granted the motion and vacated the award.
  • On appeal, the Rhode Island Supreme Court reversed the Superior Court, holding the arbitrator’s interpretation was within permissible bounds and did not manifestly disregard the law.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the arbitrator manifestly disregarded law by failing to treat the release as unambiguous waiver Release unambiguously waived all claims through Mar. 25, 2010; Max Fish supports enforcement Arbitrator reasonably distinguished Max Fish and analyzed the release language Arbitrator did not manifestly disregard law; deference applies, vacancy improper
Whether the release barred Bilray’s arbitration claims Release more stringent than Max Fish and thus bars Bilray’s claims Release ambiguous as to whom it benefits and what the requisition covered; lack of requisition precludes finding waiver Court upheld arbitrator’s finding that evidence was insufficient to conclude release extinguished claims
Whether a trial court may reweigh arbitrator’s contract interpretation Berkshire: yes, when arbitrator misreads an unambiguous release Bilray: no, courts’ review is extremely limited; only manifest disregard permits vacatur Court affirmed limited review; mere disagreement with arbitrator’s interpretation is insufficient to vacate
Proper remedy under § 10-3-12 when arbitrator errs on law Berkshire: vacatur appropriate because arbitrator erred as a matter of law Bilray: error of law alone does not meet statutory vacatur grounds absent manifest disregard Vacatur requires more than error; arbitrator’s decision stood and Superior Court’s vacatur reversed

Key Cases Cited

  • Gustafson v. Max Fish Plumbing & Heating Co., 622 A.2d 450 (R.I. 1993) (holding a subcontractor’s release unambiguously waived claims for labor and materials)
  • Prudential Property & Casualty Ins. Co. v. Flynn, 687 A.2d 440 (R.I. 1996) (arbitration awards insulated from ordinary appellate review; manifest disregard standard explained)
  • North Providence School Committee v. North Providence Federation of Teachers, 945 A.2d 339 (R.I. 2008) (strong public policy favoring finality of arbitration awards)
  • Bradford Dyeing Assn., Inc. v. J. Stog Tech GMBH, 765 A.2d 1226 (R.I. 2001) (noting mistake of law is not a statutory ground for vacating an arbitration award)
Read the full case

Case Details

Case Name: Berkshire Wilton Partners, LLC v. Bilray Demolition Co., Inc.
Court Name: Supreme Court of Rhode Island
Date Published: Jun 9, 2014
Citations: 91 A.3d 830; 2014 WL 2568282; 2014 R.I. LEXIS 84; 2013-191-Appeal
Docket Number: 2013-191-Appeal
Court Abbreviation: R.I.
Log In