History
  • No items yet
midpage
Beal Bank Nevada v. NorthShore Center THC, LLC
2016 IL App (1st) 151697
| Ill. App. Ct. | 2016
Read the full case

Background

  • Owner (Northshore) contracted with FCL (Contractor); Lake County Grading (Subcontractor) performed excavation/sewer work under a subcontract.
  • Subcontractor invoiced ~$906k total; Owner paid part but refused/failed to pay remainder; subcontractor recorded lien and later settled its lien for $475,000, reducing its claim.
  • Contractor recorded its own lien and obtained a judgment against Owner; Owner became insolvent/dissolved and contractor did not (and subcontractor did not accept) assignment of that judgment.
  • Subcontractor sued Contractor for breach of the subcontract for unpaid amounts; Contractor defended that subcontract made Contractor’s payment obligation conditional on Contractor receiving payment from Owner (a condition precedent / pay‑if‑paid).
  • Circuit court granted summary judgment for Contractor, relying on Conte to read subcontract payment clauses as a condition precedent. Subcontractor appealed.
  • Appellate court reversed: it held the subcontract required Contractor to pay Subcontractor (sections 5.1–5.2 govern timing/amounts), did not unambiguously create a condition precedent shifting owner‑nonpayment risk to Subcontractor, and interpreted Section 5.4 (advance payments) as corroborating that primary payment obligation remained with Contractor.

Issues

Issue Subcontractor's Argument Contractor's Argument Held
Whether subcontract made Contractor’s payment obligation conditional on Contractor’s receipt of payment from Owner (i.e., a pay‑if‑paid/condition precedent) Clauses regulate timing/amounts (pay‑when‑paid); no clear language shifting risk of owner nonpayment to Subcontractor, so Contractor remains obligated to pay after reasonable time Contract language (sections 5.1, 5.2) establishes Owner payment as condition precedent; Conte controls and bars recovery absent Owner payment The subcontract does not unambiguously impose a condition precedent; sections 5.1–5.2 address timing/amounts (pay‑when‑paid), and Contractor remains obligated to pay Subcontractor; summary judgment for Contractor reversed.

Key Cases Cited

  • A.A. Conte, Inc. v. Campbell-Lowrie-Lautermilch Corp., 132 Ill. App. 3d 325 (Ill. App. 1985) (upholding subcontract language construed as condition precedent/pay‑if‑paid)
  • BMD Contractors, Inc. v. Fidelity & Deposit Co. of Maryland, 679 F.3d 643 (7th Cir. 2012) (distinguishes pay‑when‑paid from pay‑if‑paid; enforces clear pay‑if‑paid clauses)
  • Killianek v. Kim, 192 Ill. App. 3d 139 (Ill. App. 1989) (contract condition precedent where final certificate required before owner’s payment obligation)
  • Coey v. Lehman, 79 Ill. 173 (Ill. 1875) (architect’s certification as condition precedent to final payment)
  • Brown & Kerr Inc. v. St. Paul Fire & Marine Ins. Co., 940 F. Supp. 1245 (N.D. Ill. 1996) (pay‑when‑paid clause does not bar recovery under surety bond; cites Mechanics Lien Act policy)
Read the full case

Case Details

Case Name: Beal Bank Nevada v. NorthShore Center THC, LLC
Court Name: Appellate Court of Illinois
Date Published: Oct 21, 2016
Citation: 2016 IL App (1st) 151697
Docket Number: 1-15-1697
Court Abbreviation: Ill. App. Ct.