992 N.W.2d 440
Neb.2023Background
- Boyle hired BCL Properties as general contractor under a written construction contract for a residential renovation; disputes arose over extra work and payments and BCL stopped work.
- BCL filed a construction lien and then sued Boyle for breach of contract, unjust enrichment, quantum meruit, and to foreclose the lien; Boyle counterclaimed for breach, misrepresentation, and UDTPA violations.
- A jury returned verdicts for BCL on its breach claim for $193,037 and against Boyle on her counterclaims; the district court entered judgment and foreclosed the lien.
- After verdict, the court held an evidentiary hearing and awarded prejudgment interest under Neb. Rev. Stat. §45-104 and attorney fees under Neb. Rev. Stat. §52-157 (Nebraska Construction Lien Act).
- Boyle moved for a new trial (challenging exclusion of two summary exhibits and the court's handling of a jury question) and to alter the judgment (challenging interest and attorney fees); the court denied relief and Boyle appealed.
- The Nebraska Supreme Court affirmed the prejudgment interest award but vacated the attorney fee award and affirmed the remainder of the judgment.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Exclusion of summary exhibits E319/E320 | Exclusion was final and prejudiced Boyle at trial | Trial court only gave preliminary ruling; Boyle could testify about the contents | Not preserved: court's pretrial/in limine ruling was not a final ruling and Boyle never offered the exhibits or made an offer of proof; no appellate review |
| Court's handling of jury question about calculating damages | Court erred by accepting verdict without answering jury question | Court intended to refer jury to written instructions; verdict reached before reply | Waived and not an abuse: Boyle failed to timely object; court's discretionary handling was not an abuse |
| Award of prejudgment interest under §45-104 | Boyle argued no "money due" because amounts disputed | BCL argued the written contract is an "instrument in writing" and money was due under jury verdict | Affirmed: construction contract is an instrument in writing under §45-104; prejudgment interest available even if claim was disputed or not liquidated |
| Award of attorney fees under §52-157 (Construction Lien Act) | Boyle argued fees not authorized because no wrongful deprivation | BCL argued foreclosure and having to sue supported fees under §52-157 | Vacated: §52-157 permits fees only when claimant is "wrongfully deprived" of benefits under the Act; mere necessity to foreclose or dispute over amounts is insufficient |
Key Cases Cited
- Echo Group v. Tradesmen Internat., 312 Neb. 729 (2022) (interpreting §52-157 and holding attorney fees require a wrongful deprivation beyond mere foreclosure)
- O'Brien v. Cessna Aircraft Co., 298 Neb. 109 (2017) (motion in limine rulings are preliminary; preservation requires offering the evidence or an offer of proof at trial)
- Prudential Ins. Co. v. Greco, 211 Neb. 342 (1982) (contracts can qualify as instruments in writing under statutes allowing prejudgment interest)
- Tilt-Up Concrete v. Star City/Federal, 261 Neb. 64 (2001) (contractor who received all benefits under the Lien Act cannot recover damages under §52-157)
- Weyh v. Gottsch, 303 Neb. 280 (2019) (prejudgment interest under §45-104 may be awarded even when claims are disputed)
