History
  • No items yet
midpage
992 N.W.2d 440
Neb.
2023
Read the full case

Background

  • Boyle hired BCL Properties as general contractor under a written construction contract for a residential renovation; disputes arose over extra work and payments and BCL stopped work.
  • BCL filed a construction lien and then sued Boyle for breach of contract, unjust enrichment, quantum meruit, and to foreclose the lien; Boyle counterclaimed for breach, misrepresentation, and UDTPA violations.
  • A jury returned verdicts for BCL on its breach claim for $193,037 and against Boyle on her counterclaims; the district court entered judgment and foreclosed the lien.
  • After verdict, the court held an evidentiary hearing and awarded prejudgment interest under Neb. Rev. Stat. §45-104 and attorney fees under Neb. Rev. Stat. §52-157 (Nebraska Construction Lien Act).
  • Boyle moved for a new trial (challenging exclusion of two summary exhibits and the court's handling of a jury question) and to alter the judgment (challenging interest and attorney fees); the court denied relief and Boyle appealed.
  • The Nebraska Supreme Court affirmed the prejudgment interest award but vacated the attorney fee award and affirmed the remainder of the judgment.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Exclusion of summary exhibits E319/E320 Exclusion was final and prejudiced Boyle at trial Trial court only gave preliminary ruling; Boyle could testify about the contents Not preserved: court's pretrial/in limine ruling was not a final ruling and Boyle never offered the exhibits or made an offer of proof; no appellate review
Court's handling of jury question about calculating damages Court erred by accepting verdict without answering jury question Court intended to refer jury to written instructions; verdict reached before reply Waived and not an abuse: Boyle failed to timely object; court's discretionary handling was not an abuse
Award of prejudgment interest under §45-104 Boyle argued no "money due" because amounts disputed BCL argued the written contract is an "instrument in writing" and money was due under jury verdict Affirmed: construction contract is an instrument in writing under §45-104; prejudgment interest available even if claim was disputed or not liquidated
Award of attorney fees under §52-157 (Construction Lien Act) Boyle argued fees not authorized because no wrongful deprivation BCL argued foreclosure and having to sue supported fees under §52-157 Vacated: §52-157 permits fees only when claimant is "wrongfully deprived" of benefits under the Act; mere necessity to foreclose or dispute over amounts is insufficient

Key Cases Cited

  • Echo Group v. Tradesmen Internat., 312 Neb. 729 (2022) (interpreting §52-157 and holding attorney fees require a wrongful deprivation beyond mere foreclosure)
  • O'Brien v. Cessna Aircraft Co., 298 Neb. 109 (2017) (motion in limine rulings are preliminary; preservation requires offering the evidence or an offer of proof at trial)
  • Prudential Ins. Co. v. Greco, 211 Neb. 342 (1982) (contracts can qualify as instruments in writing under statutes allowing prejudgment interest)
  • Tilt-Up Concrete v. Star City/Federal, 261 Neb. 64 (2001) (contractor who received all benefits under the Lien Act cannot recover damages under §52-157)
  • Weyh v. Gottsch, 303 Neb. 280 (2019) (prejudgment interest under §45-104 may be awarded even when claims are disputed)
Read the full case

Case Details

Case Name: BCL Properties v. Boyle
Court Name: Nebraska Supreme Court
Date Published: Jun 30, 2023
Citations: 992 N.W.2d 440; 314 Neb. 607; S-22-377
Docket Number: S-22-377
Court Abbreviation: Neb.
Log In
    BCL Properties v. Boyle, 992 N.W.2d 440