History
  • No items yet
midpage
Bauer v. Ready Windows Sales & Service Corp.
221 So. 3d 761
| Fla. Dist. Ct. App. | 2017
Read the full case

Background

  • In August 2013 the Bauers contracted with Ready Windows for replacement of doors and windows for $24,804.05; contract listed separate amounts for products, permit fees, and installation and stated “engineering and permit included.”
  • Ready Windows used an unlicensed drafter (not a licensed engineer) to prepare a two-dimensional plan filed for a building permit; Miami‑Dade did not require a licensed engineer for this job.
  • Installation occurred in October 2013; the Bauers later served Chapter 558 defect notices and withheld final payment, alleging defective installation and other problems.
  • Ready Windows filed a claim of lien under Chapter 713 and sued to foreclose the lien; after a bench trial the court found the contract divisible and awarded Ready Windows $9,039.05 but disallowed the $3,600 allocated for installation due to breach.
  • Both parties appealed (Bauers appealed the award to Ready Windows for products; Ready Windows cross‑appealed the setoff for installation). This Court affirmed the trial court on both appeal and cross‑appeal.
  • Both parties moved for appellate attorney’s fees under Fla. R. App. P. 9.400 and section 713.29; the court denied both motions, finding neither party was the prevailing party under the controlling test.

Issues

Issue Plaintiff's Argument (Bauers) Defendant's Argument (Ready Windows) Held
Whether either party is the prevailing party entitled to fees under §713.29 Bauers: they prevailed on appeal regarding product defects and should recover appellate fees Ready Windows: prevailed on the products claim and argued it was prevailing for fees Neither party awarded fees; under the Moritz/Prosperi significant‑issues test the court exercised discretion and found both prevailed on different significant issues so neither is sole prevailing party
Whether failure to use a licensed engineer breached the contract Bauers: “engineering” meant a licensed engineer should seal/sign plans; breach entitles them to relief Ready Windows: “engineer” used colloquially; county did not require licensed engineer for this permit Court rejected Bauers’ contention; no breach for lack of licensed engineer
Whether products (doors/windows) conformed to contract Bauers: products defective or not as promised Ready Windows: products were as represented and fit the spaces Court found products were adequate; Ready Windows entitled to amounts for products
Whether installation breached the contract Bauers: installation was defective and warranted withholding final payment and setoff Ready Windows: completed scope except minor punchlist; Bauers prevented completion Court found Ready Windows breached installation obligation and disallowed the $3,600 installation amount (setoff to Bauers)

Key Cases Cited

  • Trytek v. Gale Indus., Inc., 3 So. 3d 1194 (Fla. 2009) (adopts Moritz/Prosperi ‘‘significant issues’’ test for prevailing party under §713.29 and recognizes possibility that neither party prevails)
  • Moritz v. Hoyt Enters., Inc., 604 So. 2d 807 (Fla. 1992) (party prevailing on significant issues is the prevailing party for attorney’s fees)
  • Prosperi v. Code, Inc., 626 So. 2d 1360 (Fla. 1993) (trial court has discretion to consider equities in determining prevailing party)
  • Emery v. Int’l Glass & Mfg., Inc., 249 So. 2d 496 (Fla. 2d DCA 1971) (legislature did not intend mechanics’ lien fees where defendant defeats lien but remains liable for related labor/materials)

Motions for appellate attorney’s fees denied for both parties.

Read the full case

Case Details

Case Name: Bauer v. Ready Windows Sales & Service Corp.
Court Name: District Court of Appeal of Florida
Date Published: Jun 21, 2017
Citation: 221 So. 3d 761
Docket Number: 3D16-1171
Court Abbreviation: Fla. Dist. Ct. App.