573 S.W.3d 594
Ark. Ct. App.2019Background
- David Barnes contracted to build the Wagoners a house for $100,000 but work was incomplete/defective when he left the project.
- The Wagoners hired a replacement contractor, Johnny Jagneaux, who testified the job had multiple defects (noninterlocking blocks, wrong rebar size, structure out of square by ~4", uneven basement slab, undersized window openings, poured concrete interfering with plumbing/ducts, and prematurely installed flooring that mildewed).
- The Wagoners paid Barnes $60,000 before replacing him. They later paid Jagneaux $117,700 to correct defects and finish construction.
- The trial court found Barnes breached the contract by failing to complete work timely and in a workmanlike manner and awarded the Wagoners $77,700 (the difference between total cost $177,700 and the original contract price $100,000).
- Barnes appealed, arguing the findings were unsupported, that he had performed extra work, that no timeframe existed, and that construction standards were not established.
- The appellate court reviewed the bench findings for clear error and affirmed the trial court's judgment.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether Barnes breached the contract by failing to complete work timely and workmanlike | Wagoners: Barnes failed to complete and performed defective work, requiring corrective work by successor contractor | Barnes: He completed work per manufacturer instructions, performed extra work, no timeframe existed, and some deviations were acceptable | Court: Finding of breach not clearly erroneous; credibility and disputed facts are for the fact-finder |
| Damages — whether Wagoners proved resulting damages and amount awarded | Wagoners: Paid $60,000 to Barnes and $117,700 to replace/fix work; damages equal the excess paid over contract price ($77,700) | Barnes: Implicit challenge that amounts or scope of corrective work exceeded contractual scope or were unsupported | Court: Accepted evidence of payments and awarded $77,700 (difference between actual cost and contract price) |
| Preservation — whether Barnes may argue lack of established construction standards on appeal | Wagoners: N/A (issue was not contested at trial) | Barnes: Trial record insufficient to show required construction standards and breaches | Court: Barnes failed to raise that argument below; appellate court will not consider new arguments raised first on appeal |
Key Cases Cited
- Keith Capps Landscaping & Excavation, Inc. v. Van Horn Constr., Inc., 448 S.W.3d 207 (Ark. App. 2014) (elements of breach-of-contract claim and standard of review for bench trials)
