History
  • No items yet
midpage
Auto-Owners Ins. Co. v. Campbell-Durocher Grp. Painting & Gen. Contracting, LLC
911 N.W.2d 493
Mich. Ct. App.
2017
Read the full case

Background

  • City of Adrian contracted with Campbell-Durocher Group (general contractor) for a historic-façade restoration; Campbell-Durocher furnished payment and performance bonds with Auto‑Owners as surety and executed an indemnity agreement with Auto‑Owners.
  • Original contract completion date was December 19, 2009; a change order moved substantial completion for storefront windows/doors to May 13, 2010; work remained incomplete thereafter.
  • City terminated Campbell‑Durocher from the job on August 24, 2010, citing noncompletion, unpaid supplier, and unresolved storefront issues; City submitted a bond claim to Auto‑Owners.
  • Auto‑Owners paid bond claims (approx. $127,000 to City; $62,000 to ABC Supply) and sought indemnification from the Campbells for ~$189,277 plus costs and fees under the indemnity agreement.
  • Campbells sued the City for breach of contract (seeking ~$59,624 allegedly unpaid and damages for termination without 90 days’ notice); multiple summary‑disposition motions followed and appeals were taken after the trial court denied Auto‑Owners’ and the City’s motions.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether Auto‑Owners is entitled to summary judgment on its contractual indemnification claim Auto‑Owners: indemnity agreement unambiguously requires Campbells to reimburse all bond losses; Auto‑Owners’ payments are prima facie evidence of liability Campbells: Auto‑Owners paid in bad faith without proper investigation and therefore cannot recover Held: Reversed trial court; Auto‑Owners entitled to summary disposition because indemnity language is clear, payments are prima facie evidence, and Campbells failed to present specific evidence of bad faith
Whether City was entitled to summary judgment on Campbells’ breach‑of‑contract claim City: contract expired (Dec 19, 2009 or May 13, 2010 by change order), so §2.2 90‑day notice did not apply and termination in Aug 2010 was not a breach Campbells: parties continued performance after May 2010 creating an implied extension; Campbells also seek payment for work performed before termination Held: Affirmed trial court’s denial as to City; genuine issues of fact exist about implied extension, applicability of 90‑day notice, and unpaid work

Key Cases Cited

  • Ajax Paving Indus., Inc. v. Vanopdenbosch Const. Co., 289 Mich. App. 639 (contract interpretation governs indemnity agreements)
  • Meagher v. Wayne State Univ., 222 Mich. App. 700 (clear contract language is a question of law)
  • Kyocera Corp. v. Hemlock Semiconductor, LLC, 313 Mich. App. 437 (contract interpretation aims to honor parties’ intent)
  • Title Guaranty & Surety Co. v. Roehm, 215 Mich. 586 (indemnity contracts construed to cover intended losses)
  • P.R. Post Corp. v. Maryland Cas. Co., 403 Mich. 543 (prima facie evidence shifts burden to indemnitor)
  • Miller v. Riverwood Recreation Ctr., Inc., 215 Mich. App. 561 (definition of good faith and bad faith in related contexts)
  • Transamerica Ins. Co. v. Bloomfield, 401 F.2d 357 (enforceability of indemnity clauses allocating settlement risk)

Outcome: Trial court denial of Auto‑Owners’ motion reversed (Auto‑Owners entitled to indemnification absent evidence of bad faith); trial court denial of City’s motion affirmed (fact questions about contract extension and 90‑day notice remain).

Read the full case

Case Details

Case Name: Auto-Owners Ins. Co. v. Campbell-Durocher Grp. Painting & Gen. Contracting, LLC
Court Name: Michigan Court of Appeals
Date Published: Oct 12, 2017
Citation: 911 N.W.2d 493
Docket Number: No. 331384; No. 331389; No. 331802; No. 331803
Court Abbreviation: Mich. Ct. App.