History
  • No items yet
midpage
Atlas Sahil Construction Company
ASBCA No. 58951
| A.S.B.C.A. | Nov 9, 2017
Read the full case

Background

  • Atlas Sahil (contractor) was awarded a firm‑fixed‑price design‑build contract to expand FOB Deh Dadi II in Afghanistan, including nine 90x120 maintenance tents, generators, power distribution, and earthwork.
  • The contract included FAR 52.249‑2 Termination for Convenience (Alternate I) and incorporated FAR Part 31 cost principles.
  • Work was suspended in April 2011; the contract was descoped by modification (reduced tent installation, reduced footprint, added CLIN 0029), then a notice to proceed issued in Dec. 2011; the contract was terminated for convenience in March 2012.
  • Atlas Sahil delivered nine damaged tents (no electrical/HVAC installed) and submitted a termination settlement claim seeking about $4.16M; the government challenged documentation, authenticity, and many cost items.
  • The Board found some records unreliable, Sambros (JV partner/supplier) held additional records that Atlas Sahil did not produce, and Atlas Sahil never broke ground nor obtained final design approval.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Applicability of standard termination clause (Christian doctrine) Christian doctrine should incorporate the standard FAR termination clause rather than Alternate I because performance included supply elements Contract already included Alternate I; no regulation required replacing Alternate I with the standard clause Rejected plaintiff; Alternate I governs (no automatic substitution under Christian)
Measure of recovery (CLIN pricing vs cost/jury‑verdict method) CLIN pricing (and if needed, jury‑verdict approximation) is proper because CLINs reflect agreed value and plaintiff cannot fully document costs Termination settlements are cost‑based; contractor bears burden to prove costs; plaintiff has not shown justifiable inability to substantiate costs to warrant jury verdict Rejected CLIN/priced approach and jury verdict; used available cost evidence and contracting officer analysis to determine reasonable costs
Tent cost and delivery amounts Entitled to CLIN price for nine tents ($1,647,000) and related delivery costs Al Baddad invoice ($747,000) and shipment documents are reliable; CLIN price includes installation no longer required after modification Allowed $747,000 for tents; allowed $336,244 for shipment/delivery (supported by invoices)
Recoverability and quantum of other cost categories (labor, office, CLIN 0029, DBA, severance, legal, profit) Various higher amounts claimed (e.g., large labor, office rent, high profit) Many costs unsupported or unreasonable (excess staffing, costs during suspension, inflated salaries); FAR Part 31 reasonableness test applies Allowed: CLIN 0029 $129,120; labor $40,270 (contracting officer estimate); office $12,000; DBA $28,663; administrative $55,416.60; severance $49,525 (allowed under Afghan law); legal $40,792; profit 5% on allowable costs; total award $1,503,695.45 plus interest

Key Cases Cited

  • G.L. Christian & Associates v. United States, 312 F.2d 418 (Ct. Cl. 1963) (establishes Christian doctrine for mandatory inclusion of required clauses)
  • General Engineering & Machine Works v. O'Keefe, 991 F.2d 775 (Fed. Cir. 1993) (Christian doctrine does not automatically incorporate every required clause)
  • Grumman Aerospace Corp. v. Wynne, 487 F.3d 1350 (Fed. Cir. 2007) (criteria for when a jury‑verdict method of approximating damages is permissible)
  • Lisbon Contractors, Inc. v. United States, 828 F.2d 759 (Fed. Cir. 1987) (contractor bears burden to prove fact and amount of loss with sufficient certainty)
Read the full case

Case Details

Case Name: Atlas Sahil Construction Company
Court Name: Armed Services Board of Contract Appeals
Date Published: Nov 9, 2017
Docket Number: ASBCA No. 58951
Court Abbreviation: A.S.B.C.A.