History
  • No items yet
midpage
Asset Recovery Contracting, LLC v. Walsh Construction Company of Illinois
980 N.E.2d 708
Ill. App. Ct.
2012
Read the full case

Background

  • ARC entered a subcontract with Walsh to perform interior demolition at the Palmolive Building redevelopment, dated September 12, 2003; ARC executed March 19, 2004 and Walsh executed May 5, 2004.
  • The project faced CFD order delaying demolition and Arden Agreement restrictions, plus financing and tenant occupancy issues affecting the schedule.
  • Exhibit J rider modified time-related terms, including Walsh's right to adjust sequence and pace without monetary compensation and an altered claims process for any Subcontractor requests.
  • Revised schedules in October 2003 and January 2004 extended ARC’s work; ARC reviewed cost projections but did not initially seek delay damages.
  • Section 5.1 of the subcontract waived damages from site-resource allocations; Section 1.2 limited ARC’s rights to those provided in the subcontract; the prime contract limited delay damages and set time-extension as the sole remedy absent intentional interference.
  • ARC sought delay damages and destruction-of-business damages; the trial court struck the destruction claim and the appellate court ultimately affirmed barring delay damages and rejecting extrinsic-evidence errors.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether extrinsic evidence was properly used to interpret the subcontract's effective date and schedule ARC contends extrinsic evidence should not alter the contract terms. Walsh argues extrinsic evidence is permissible to interpret schedule and effective date when ambiguity exists. Extrinsic evidence permitted for ambiguity; date ambiguity not required to be resolved, but harmless error on date.
Whether no damages for delay barred ARC's damages despite owner delays and schedule changes ARC seeks delay damages due to owner-caused delays not contemplated by the parties. No damages for delay clause bars such damages; carve-outs do not apply here. Delay damages barred; exceptions not satisfied; ARC waived by conduct and contract.
Whether ARC's destruction of business claim could be struck ARC contends destruction of business damages are recoverable under contract principles. Consequence damages are barred by the subcontract and prime contract. Destruction of business damages struck; barred by no-damages-for-consequential clause.

Key Cases Cited

  • Armstrong Paint & Varnish Works v. Continental Can Co., 301 Ill. 102 (Illinois 1921) (four-corners rule; parol evidence limited to ambiguities)
  • River’s Edge Homeowners’ Ass’n v. City of Naperville, 353 Ill. App. 3d 874 (Ill. App. 1st Dist. 2004) (ambiguity requires extrinsic evidence; de novo contract interpretation)
  • J&B Steel Contractors, Inc. v. C. Iber & Sons, Inc., 162 Ill. 2d 265 (Ill. 1994) (parol evidence allowed for schedule changes not contradicting fully integrated contract)
  • Monahan v. Fidelity Mutual Life Insurance Co., 148 Ill. App. 171 (Ill. 1909) (effective date principles in contract execution)
  • Grubb & Ellis Co. v. Bradley Real Estate Trust, 909 F.2d 1050 (7th Cir. 1990) (relation back of contract terms to earlier coverage; integration context)
Read the full case

Case Details

Case Name: Asset Recovery Contracting, LLC v. Walsh Construction Company of Illinois
Court Name: Appellate Court of Illinois
Date Published: Nov 1, 2012
Citation: 980 N.E.2d 708
Docket Number: 1-10-1226
Court Abbreviation: Ill. App. Ct.