History
  • No items yet
midpage
Aspic Engineering and Constr. v. Ecc Centcom Constructors LLC
913 F.3d 1162
| 9th Cir. | 2019
Read the full case

Background

  • ECC (prime contractor to USACE) awarded two Afghanistan construction subcontracts to Aspic; the subcontracts incorporated FAR clauses (including termination-for-convenience provisions) and a pass-through clause making Aspic subject to the same obligations ECC owed the government.
  • USACE terminated ECC’s prime contracts for convenience; ECC terminated the two subcontracts and Aspic submitted termination settlement proposals but lacked many required FAR-style supporting materials and translations.
  • USACE refused to pay ECC for subcontractor termination costs after an audit and later executed a no-cost settlement with ECC; ECC likewise refused Aspic’s settlement demands, prompting Aspic to arbitrate.
  • The arbitrator awarded Aspic about $1,072,520, concluding Aspic need not meet the FAR requirements because (the arbitrator found) there was no true meeting of the minds and Aspic was a less-sophisticated Afghan subcontractor with different practices.
  • California superior court confirmed and modified the award (awarding attorneys’ fees); ECC removed to federal court and the district court vacated the arbitration award as conflicting with the subcontract text; the Ninth Circuit affirmed.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether the arbitrator exceeded his powers by relieving Aspic of FAR compliance incorporated in the subcontracts Arbitrator lawfully interpreted contract and parties’ conduct showed they did not expect Aspic to meet strict FAR procedures Arbitrator ignored clear contract text and pass-through FAR obligations, exceeding authority Held: Arbitrator exceeded powers; vacatur affirmed — award did not draw its essence from the contract
Whether parties’ past practices justified modifying or waiving FAR requirements Aspic: informal Afghan practices and submitted handwritten receipts show de facto waiver or modification ECC: no evidence of any past practice deviating from FAR; parties briefed FAR applicability Held: No past-practice evidence supported departure; arbitrator relied on perceived unfairness rather than demonstrated practice
Whether an arbitrator may disregard explicit contract provisions to avoid an unjust result Aspic: arbitrator may correct contractual unfairness based on context and parties’ intent ECC: arbitrator cannot dispense his own brand of justice by ignoring express terms Held: Arbitrator impermissibly disregarded explicit provisions to reach a result he deemed fair; that is irrational
Whether the fee award issue requires review given vacatur Aspic: argued arbitrator erred in denying attorneys’ fees and arbitration costs ECC: vacatur moots Aspic’s fee arguments Held: Fee issue moot because Award vacated

Key Cases Cited

  • First Options of Chicago, Inc. v. Kaplan, 514 U.S. 938 (Sup. Ct.) (standard of de novo review for arbitrability and role of courts in arbitration review)
  • Bosack v. Soward, 586 F.3d 1096 (9th Cir.) (award must draw its essence from the contract; limits on judicial review)
  • Comedy Club, Inc. v. Improv W. Assocs., 553 F.3d 1277 (9th Cir.) (arbitral review is limited and highly deferential; irrational awards vacatable)
  • Kyocera Corp. v. Prudential-Bache Trade Servs., Inc., 341 F.3d 987 (9th Cir.) (arbitrator exceeds powers when award is completely irrational or shows manifest disregard)
  • Pacific Motor Trucking Co. v. Automotive Machinists Union, 702 F.2d 176 (9th Cir.) (arbitrator may not disregard explicit contract provisions to correct perceived injustices)
  • United Steelworkers of Am. v. Enterprise Wheel & Car Corp., 363 U.S. 593 (Sup. Ct.) (arbitrator cannot dispense his own brand of industrial justice)
Read the full case

Case Details

Case Name: Aspic Engineering and Constr. v. Ecc Centcom Constructors LLC
Court Name: Court of Appeals for the Ninth Circuit
Date Published: Jan 28, 2019
Citation: 913 F.3d 1162
Docket Number: 17-16510
Court Abbreviation: 9th Cir.