History
  • No items yet
midpage
Arrowood Indemnity Co. v. MacOn County Greyhound Park, Inc.
757 F. Supp. 2d 1219
M.D. Ala.
2010
Read the full case

Background

  • MCGP carried a primary $1 million USF&G policy and an excess Big Shield policy for up to $5 million, the latter requiring timely notice to Arrowood.
  • Ronnie Lawrence slipped in MCGP restroom in 2003, triggering occurrence and potential claim under the excess policy.
  • Lawrence filed a state-court suit in 2005 seeking damages for back and neck injuries; his case valued at around $1 million by defendants' side over time.
  • By 2007–2008, mediation and discovery indicated a high verdict was reasonably likely, with Lawrence demanding amounts near or exceeding the primary policy limits.
  • Arrowood was not notified of the Lawrence suit until February 26, 2008, nearly two weeks after a $1.5 million verdict had been returned and after the verdict was affirmed on appeal.
  • Arrowood filed this declaratory judgment action in October 2008 seeking to be relieved of indemnity due to late notice; Macon County cross-moved for summary judgment.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether late notice was unreasonable as a matter of law Arrowood claims delayed notice violated VIII(5)(d) and was prejudicial. MCGP asserts two-week post-verdict notice was timely under the policy and reasonable given facts. Unreasonable delay as a matter of law; prejudice shown
Whether the savings clause shielded MCGP from prejudice Savings clause protects only if delay caused by reasonable belief not covered; here belief was unreasonable. Savings clause should protect if belief was reasonable and delay due to belief the claim wasn't covered. Savings clause does not apply; delay unreasonable and not due to reasonable belief
Whether Arrowood was prejudiced by MCGP's failure to provide notice Delay deprived Arrowood of settlement involvement and reserve setting. No prejudice argument relies on potential actions; Arrowood's participation was possible if timely notified. Arrowood prejudiced; contractual rights lost, prejudice established
Whether Arrowood properly refused to indemnify under the contract Timely notice was not provided; thus indemnity should not apply. If notice was timely, Arrowood would indemnify; delay defeats this. Arrowood entitled to summary judgment; MCGP's breach established

Key Cases Cited

  • Pan American Fire & Cas. Co. v. DeKalb-Cherokee Counties Gas District, 266 So.2d 763 (Ala. 1972) (objective test for notice requirement under policy)
  • Evanston Ins. Co. v. Stonewall Surplus Lines Ins. Co., 111 F.3d 852 (11th Cir. 1997) (insured's appraisal controls only if reasonable; excess carriers not entitled to notice of every claim)
  • Midwest Employers Cas. Co. v. East Alabama Health Care, 695 So.2d 1169 (Ala. 1997) (prejudice required for excess insurer disclaimer)
  • Lemuel v. Admiral Ins. Co., 414 F.Supp.2d 1037 (M.D. Ala. 2006) (prejudice analysis for late notice; reserves and settlement impact)
  • Haston v. Transamerica Ins. Servs., 662 So.2d 1138 (Ala. 1995) (two factors for reasonableness: length of delay and reasons)
  • Thomas, 334 So.2d 883 (Ala. 1976) (six-month delay unreasonable as a matter of law)
Read the full case

Case Details

Case Name: Arrowood Indemnity Co. v. MacOn County Greyhound Park, Inc.
Court Name: District Court, M.D. Alabama
Date Published: Dec 3, 2010
Citation: 757 F. Supp. 2d 1219
Docket Number: Case 3:08-cv-812-MEF
Court Abbreviation: M.D. Ala.