History
  • No items yet
midpage
Archon Construction Co. Inc. v. U.S. Shelter, LLC
2017 IL App (1st) 153409
| Ill. App. Ct. | 2017
Read the full case

Background

  • Archon contracted with U.S. Shelter to install a sanitary sewer system for the Oak Ridge subdivision; the contract incorporated city Plans and specifications requiring the sewer be accepted by the City of Elgin and to be televised one year after completion.
  • Archon’s proposal specified PVC (SDR 26) pipe and included an item for testing/televising and a clause that additional work would be on negotiated price or time-and-materials.
  • After completion and initial testing in 2005 (air and mandrel tests passed), later videotaping in 2007 revealed defects between MH 108 and MH 110; the city required excavation and replacement with ductile iron pipe.
  • Archon performed the required replacement work and submitted a bill (~$247,432.41) for the MH 108–110 work; U.S. Shelter refused to pay. Archon dropped its contractual “extra work” claims on remand and proceeded to trial on quantum meruit only.
  • The trial court ruled for U.S. Shelter on quantum meruit (holding an express contract governed the subject matter) and for Archon on U.S. Shelter’s counterclaim for restoration costs; both parties appealed.
  • The appellate court affirmed: quantum meruit was barred because the express contract governed the same general subject matter; the trial court’s rejection of U.S. Shelter’s breach-of-contract counterclaim was not against the manifest weight of the evidence.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether Archon may recover under quantum meruit for the 2007 repairs (replacement with ductile iron) Archon: work (ductile iron) was outside the contract (contract specified PVC); thus quantum meruit or recovery allowed. U.S. Shelter: an express contract governed installation and final acceptance of a sewer acceptable to the city, so quasi-contractual recovery is barred. Court: Denied Archon—quantum meruit barred because the express contract governed the same general subject matter (installation/acceptance of the sewer).
Whether U.S. Shelter proved breach of contract by Archon causing restoration damages after 2007 excavation U.S. Shelter: Archon’s earlier defective work (fittings, couplings, compaction) caused later defects and resulting restoration costs. Archon: defects found in 2007 were not proven to be caused by Archon’s earlier work; many intervening events could explain them. Court: Denied U.S. Shelter—failed to prove causal link; trial court’s finding supported by the evidence.

Key Cases Cited

  • People v. Kinion, 97 Ill. 2d 322 (1983) (existence of express contract bars quantum meruit)
  • Industrial Lift Truck Service Corp. v. Mitsubishi Int’l Corp., 104 Ill. App. 3d 357 (1982) (work within the general subject matter of a contract precludes quasi-contract recovery)
  • Walker v. Brown, 28 Ill. 378 (1862) (animating principle that express and implied contracts for the same thing cannot coexist)
  • Avery v. State Farm Mut. Auto. Ins. Co., 216 Ill. 2d 100 (2005) (interpretation of unambiguous contract is a question of law reviewed de novo)
  • Installco, Inc. v. Whiting Corp., 336 Ill. App. 3d 776 (2002) (elements and limits of quantum meruit recovery)
  • Doornbos Heating & Air Conditioning, Inc. v. James D. Schlenker, M.D., S.C., 403 Ill. App. 3d 468 (2010) (elements for contractual extra-work claims)
Read the full case

Case Details

Case Name: Archon Construction Co. Inc. v. U.S. Shelter, LLC
Court Name: Appellate Court of Illinois
Date Published: Jul 14, 2017
Citation: 2017 IL App (1st) 153409
Docket Number: 1-15-3409
Court Abbreviation: Ill. App. Ct.