History
  • No items yet
midpage
214 Cal. App. 4th 329
Cal. Ct. App.
2013
Read the full case

Background

  • Webcor entered GMP contract with Wilshire for a 23-story condo project; GMP initially $65.5M, later increased to about $81M via change orders, with Webcor asserting a $13.5M additional entitlement.
  • Webcor filed breach of contract and mechanism’s lien actions against Wilshire and many unit owners; a settlement later involved Wilshire alter ego defendants.
  • As part of settlement, $32M stipulated judgment against Wilshire, but with carve-outs stating it would not offset the lien against unit owners and that alter egos would cooperate on the lien.
  • Settlement also adopted PCCO 50 raising GMP value to $95.5M for labor and services provided under the GMP contract; unit owners contested this value.
  • Before trial, the court ruled the lien amount would be based on the reasonable value of Webcor’s work, excluding contract-based defenses, citing ECC, which the court treated as controlling.
  • The unit owners sought relief by writ, arguing ECC conflicted with the statute; the court stayed, and this court granted relief to allow evidence on GMP value; on remand, taxpayer court to apply former §3123(a) to determine lien as lesser of contract price or reasonable value.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
How does former §3123(a) set lien value when owner is non-party to contract? Webcor: contract price should control; §3123(a) favors contract price as ceiling. Unit owners: ECC dictates value based on reasonable value only when owner is non-party. Statute allows lesser of contract price or reasonable value; ECC dicta rejected.
Is the GMP agreement's 'agreed price' relevant to lien amount after settlement? Value set by PCCO 50 should govern lien. Settlement mechanics artificially set value; not binding for lien amount. Remand proper to determine if settlement conclusively fixes GMP value.
Did ECC’s treatment of §3123(a) bind the trial court or is it dicta? ECC is controlling precedent for non-party owner scenario. ECC dicta; not binding. ECC's discussion deemed persuasive but dicta; not binding; reversal of misapplication.
May settlement evidence establish the agreed GMP price for lien purposes on remand? Settlement agreement can determine agreed price. Collateral agreement, assets insolvent; not conclusive. Remand permitted to allow evidence and decide if agreement conclusively fixes GMP value.

Key Cases Cited

  • ECC Construction, Inc. v. Ganson, 82 Cal.App.4th 572 (Cal. App. 2000) (lien value when owner not party to contract and other issues; dicta on §3123(a))
  • Connolly Development, Inc. v. Superior Court, 17 Cal.3d 803 (Cal. 1976) (mechanic’s lien attachment and scope under lien law)
  • Roberts v. Spires, 195 Cal. 267 (Cal. 1925) (contract price as limit of liens under lien law)
  • Forsgren Associates, Inc. v. Pacific Golf Community Development LLC, 182 Cal.App.4th 135 (Cal. App. 2010) (statutory interpretation of lien value and contract terms)
  • Britton v. Dallas Airmotive, Inc., 153 Cal.App.4th 127 (Cal. App. 2007) (statutory construction principles)
Read the full case

Case Details

Case Name: Appel v. Superior Court
Court Name: California Court of Appeal
Date Published: Mar 11, 2013
Citations: 214 Cal. App. 4th 329; 153 Cal. Rptr. 3d 798; 2013 WL 870983; 2013 Cal. App. LEXIS 180; No. B244590
Docket Number: No. B244590
Court Abbreviation: Cal. Ct. App.
Log In
    Appel v. Superior Court, 214 Cal. App. 4th 329