History
  • No items yet
midpage
Appeal by Grande Land, L.P. from the Decisions of the North Manheim Twp. ZHB Dated June 28, 2016
228 C.D. 2017
Pa. Commw. Ct.
Nov 17, 2017
Read the full case

Background

  • Grande Land owns a 12.9-acre parcel in North Manheim Township (R-2 zoning) and sought a special-exception to build a 72-unit multi‑family apartment complex.
  • The proposed site plan showed eight buildings, public water and sewer access, and stated ~25.5% open space on the 12.9‑acre tract; Grande Land also agreed to maintain two adjacent common parcels (7.1 and 4.3 acres).
  • At the Zoning Hearing Board (ZHB) hearing Grande Land introduced a Planning Module (prepared by a prior developer), site and lighting plans, and surveyor testimony (Bensinger) that public sewer was available and open space requirements were met.
  • ZHB denied the application, finding Grande Land failed to show DEP approval/adequate sewage disposal evidence, failed to prove building lengths did not exceed the 128‑ft maximum, and that open space calculations improperly included basins/wetlands and sloped areas >20%.
  • The trial court affirmed the ZHB. On appeal, this Court reviewed whether the ZHB/trial court erred as a matter of law or abused discretion.
  • Court held: ZHB erred on sewage (504.2) and building‑length (504.4(a)) issues, but did not err on open‑space (504.4(j)); trial court’s denial of the application was affirmed because the open‑space failure was a proper ground for denial.

Issues

Issue Plaintiff's Argument Defendant/ZHB/Intervenors' Argument Held
Whether Section 504.2 required DEP approval for sewage at special‑exception stage Grande: ordinance requires showing a type of sewage system acceptable to DEP; site evidence and Planning Module suffice and DEP approval can be conditioned later ZHB/Intervenors: Planning Module is outdated and does not show DEP approval or capacity for 72 units; applicant must show DEP approval as prerequisite Held: Applicant need only show it will use a method "regularly approved by DEP" (Drumore Crossings). ZHB erred in ruling Grande Land failed 504.2
Whether Grande Land proved proposed building lengths comply with 128‑ft maximum (504.4(a)) Grande: Site and Lighting Plans (admitted into evidence) show building dimensions comply ZHB/Intervenors: No testimony established lengths; ZHB not required to search exhibits; dimensions may change Held: Exhibits in the record showed none of the buildings exceed 128 ft. ZHB erred in finding noncompliance
Whether proposed common open space meets 25% and excludes prohibited features (504.4(j)) Grande: Calculations on the 12.9‑acre tract meet requirement; wetlands need not be excluded; Township will accept maintenance/dedication ZHB/Intervenors: Testimony was equivocal; exhibits show detention basins and steep slopes (>20%) within designated open space; no evidence of required perpetual preservation agreement Held: ZHB’s finding that open space calculation was unsupported by substantial evidence stands. Grande Land failed to meet 504.4(j), and this suffices to affirm denial

Key Cases Cited

  • In re Drumore Crossings, L.P., 984 A.2d 589 (Pa. Cmwlth. 2009) (applicant satisfies ordinance by showing proposed sewage method is one regularly approved by DEP; specific DEP permit need not be presented at zoning stage)
Read the full case

Case Details

Case Name: Appeal by Grande Land, L.P. from the Decisions of the North Manheim Twp. ZHB Dated June 28, 2016
Court Name: Commonwealth Court of Pennsylvania
Date Published: Nov 17, 2017
Docket Number: 228 C.D. 2017
Court Abbreviation: Pa. Commw. Ct.