165 Ohio Misc. 2d 1
Oh. Muni. Ct., Cleveland2011Background
- Kirk Bros. Co. was the prime contractor for a Marysville water reclamation plant project; Alltank was a subcontractor and Grant Systems was an additional subcontractor.
- Plaintiff expected Grant to deliver and install a duplex pump set and piping to feed an emergency generator, for the plant's April 21, 2009 grand opening.
- Purchase orders were issued in March and November 2008, and Alltank paid Grant $66,231.37 in early 2009.
- Grant delivered the duplex pump set, but it did not function to Alltank’s satisfaction; Phoenix Environmental performed last-minute work to fix it for the opening.
- Alltank billed Grant $1,845.33 for Phoenix’s and its own on-site work, but Grant refused payment after July and December 2009 invoices.
- There was no written contract; the court found an oral contract based on Grant’s November 25, 2008 quotation and subsequent dealings, and ultimately entered judgment for Grant.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether an oral contract existed and defined scope of work | Alltank argues an implied oral contract encompassed installation/start-up work. | Grant contends it delivered only the pump set; installation/start-up not included per quotation. | Oral contract found; scope limited by quotation; defendant not liable for turn-key work. |
| Whether plaintiff proved damages/entitlement to payment | Alltank seeks payment for Phoenix’s and its own on-site work to fix the system. | Grant argues no contract obligates payment for post-delivery start-up work. | Plaintiff failed to prove by a preponderance; judgment for defendant on costs. |
Key Cases Cited
- In re Lieberman, 163 Ohio St. 35 (1955) (credibility and weight of evidence principles)
- Bowlin v. Black & White Cab Co., 7 Ohio App.2d 133 (1966) (quality of evidence over quantity)
- State v. DeHass, 227 N.E.2d 212 (Ohio Sup. Ct. 1967) (testimony credibility standard)
- Marshall v. Beach, 758 N.E.2d 247 (Ohio App.3d 2001) (offer, acceptance, and consideration elements)
- Helle v. Landmark, Inc., 472 N.E.2d 765 (Ohio App.3d 1984) (contract interpretation and ambiguity resolution)
- Long Beach Assn., Inc. v. Jones, 697 N.E.2d 208 (Ohio Sup. Ct. 1998) (contract interpretation standard)
- Graham v. Drydock Coal Co., 667 N.E.2d 949 (Ohio Sup. Ct. 1996) (contract interpretation principles)
- State ex rel. Parsons v. Fleming, 628 N.E.2d 1377 (Ohio Sup. Ct. 1994) (statutory and contractual interpretation context)
- Davis v. Loopco Industries, Inc., 609 N.E.2d 144 (Ohio Sup. Ct. 1993) (extrinsic evidence in contract interpretation)
- Inland Refuse Transfer Co. v. Browning-Ferris Indus. of Ohio, Inc., 474 N.E.2d 271 (Ohio App. 1984) (extrinsic evidence and contract construction)
- Karabin v. State Auto. Mut. Ins. Co., 462 N.E.2d 403 (Ohio Sup. Ct. 1984) (contract interpretation under Ohio law)
- Eagle v. Fred Martin Motor Co., 2004-Ohio-829 (Ohio App. 2004) (contract interpretation and standard of review)
- Certified Computer v. Rieth & Antonelli Co., 2005-Ohio-5936 (Ohio Misc. 2005) (oral vs. written contract and enforceability)
