History
  • No items yet
midpage
2011 Ohio 2627
Ohio Ct. App.
2011
Read the full case

Background

  • AED and Allied Gator sued Ohio Edison for specific performance and accounting related to a substation project and transformer procurement.
  • The April 21, 2006 meeting allegedly created an overarching design-build agreement for the substation, with Ohio Edison to design and procure and to solicit bids, and a cost-plus markup discussed as part of the deal.
  • On May 1–8, 2006, a written contract for design/procurement of two transformers was signed at a price of $833,657.52, reviewed by counsel for both sides.
  • In August 2006, Ohio Edison indicated a 27% markup, not the 15% discussed, causing Allied to object and end negotiations on the substation project.
  • Allied amended its complaint in May 2007 seeking an accounting of Ohio Edison’s actual costs for the transformers and asserting breach of the April 21, 2006 discussions.
  • OE filed counterclaims for declaratory judgment that no overarching design-build contract existed and for breach of the transformer contract seeking the unpaid balance of $166,731.50 plus interest.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether parol evidence admissibly explains an overarching contract. Allied argues the April 21 discussions show a broader design-build agreement. Ohio Edison contends the transformer contract is integrated and independent of any oral design-build agreement. Parol evidence to prove overarching agreement is barred; contract is wholly integrated and unambiguous.
Whether the transformer contract is a complete integration or partial integration allowing outside evidence. Transformer contract is not fully integrated and should permit extrinsic evidence of April 21 discussions. Transformer contract is a complete integration with an integration clause, so parol evidence cannot vary its terms. Transformer contract is wholly integrated; no partial integration; no extrinsic terms admitted.
Whether Allied’s promissory fraud claim was properly alleged and admissible given parol evidence rules. Ohio Edison allegedly promised cost-plus-fifteen percent reliance on that promise. No fraud claim pled with particularity; even if pled, elements of fraud are not met and parol evidence cannot override signed writing. Fraud claim waived for lack of particularity and fails on elements; no reversible error on summary judgment for that issue.

Key Cases Cited

  • Center Ridge Ganley, Inc. v. Stinn, 31 Ohio St.3d 310 (1987) (parol evidence can explain, not vary, ambiguity; contingent relationships may be explained by extrinsic evidence)
  • Galmish v. Cicchini, 90 Ohio St.3d 22 (2000) (parol evidence admissible to prove fraud; integration clause does not bar fraud evidence)
  • TRINOVA Corp. v. Pilkington Bros., P.L.C., 70 Ohio St.3d 271 (1994) (partial vs. complete integration; four-corners analysis; consistent additional terms may be added)
  • Marion Prod. Credit Assn. v. Cochran, 40 Ohio St.3d 265 (1988) (fraud elements; averment of fraud must be with particularity)
  • Williams v. Spitzer Autoworld Canton, L.L.C., 122 Ohio St.3d 546 (2009) (parol evidence rule and integration considerations in contract disputes)
  • Bellman v. Am. Internatl. Group, 113 Ohio St.3d 323 (2007) (parol evidence rule; integration clauses; contract interpretation guidance)
  • Ed Schory & Sons, Inc. v. Francis, 75 Ohio St.3d 433 (1996) (parol evidence rule and extrinsic evidence principles)
Read the full case

Case Details

Case Name: Allied Erecting & Dismantiling Co., Inc. v. Ohio Edison Co.
Court Name: Ohio Court of Appeals
Date Published: May 26, 2011
Citations: 2011 Ohio 2627; 10-MA-25
Docket Number: 10-MA-25
Court Abbreviation: Ohio Ct. App.
Log In
    Allied Erecting & Dismantiling Co., Inc. v. Ohio Edison Co., 2011 Ohio 2627