Alexander v. Express Energy Services Operating, L.P.
784 F.3d 1032
| 5th Cir. | 2015Background:
- Michael Alexander was a lead hand/operator in Express Energy’s plug-and-abandonment (P&A) crew that plugs wells on fixed offshore platforms.
- On August 11, 2011 he was injured on an Apache-owned fixed platform while a liftboat (L/B RAM X) was positioned adjacent to the platform and connected by a catwalk; the liftboat’s crane (operated by its crew) dropped equipment that struck Alexander’s foot.
- Alexander sued under the Jones Act, asserting seaman status against Express; Express moved for summary judgment arguing Alexander was a platform-based (land-based) worker and not a seaman.
- Controlling law (Chandris test): (1) worker must do the ship’s work (contribute to vessel function or mission), and (2) must have a substantial connection to a vessel in navigation in duration and nature (Fifth Circuit rule of thumb: ordinarily ~30% of work time aboard vessel).
- Alexander argued he contributed to the liftboat’s function and relied on Roberts to count all time on jobs that used an adjacent vessel toward the 30% temporal requirement, but produced no evidence that he personally spent 30% of his time actually working on a vessel.
- The district court granted summary judgment for Express (finding failure on the contribution prong and noting temporal problems); the Fifth Circuit affirmed on the temporal-connection ground: Alexander failed to show he actually worked on a vessel at least 30% of the time.
Issues:
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether Alexander’s duties contributed to the function or mission of a vessel (Chandris prong 1) | His P&A duties supported operations that used an adjacent liftboat, so he "did the ship’s work" for the vessel | His work was performed on fixed platforms; duties related to the platform not the vessel | Court affirmed district court’s judgment on other grounds but noted Alexander did not meet the temporal prong; district court had found duties like Hufnagel (platform-based) did not contribute to vessel function |
| Whether Alexander had the required substantial temporal connection to a vessel in navigation (Chandris prong 2) | Roberts permits counting entire jobs that used an adjacent vessel toward the 30% requirement even if plaintiff worked mostly on the platform | Alexander did not present evidence he actually spent ≥30% of his work time aboard a vessel; many jobs used no adjacent vessel | Held: Alexander failed to show he actually worked on a vessel at least ~30% of the time; Roberts cannot override Chandris; summary judgment for Express affirmed |
Key Cases Cited
- Chandris, Inc. v. Latsis, 515 U.S. 347 (1995) (two-prong seaman test: ship’s work and substantial temporal/nature connection)
- McDermott Int’l, Inc. v. Wilander, 498 U.S. 337 (1991) (broad category of doing the ship’s work informs seaman inquiry)
- Barrett v. Chevron, U.S.A., Inc., 781 F.2d 1067 (5th Cir. 1986) (worker must be permanently assigned to vessel or perform a substantial portion of work aboard it)
- Hufnagel v. Omega Serv. Indus., Inc., 182 F.3d 340 (5th Cir. 1999) (platform-based duties do not constitute contribution to vessel function)
- Roberts v. Cardinal Servs., Inc., 266 F.3d 368 (5th Cir. 2001) (addressed temporal counting for adjacent-vessel jobs; Court here rejects broad application to override Chandris)
- Nunez v. B&B Dredging, Inc., 288 F.3d 271 (5th Cir. 2002) (noting temporal requirement; worker must spend substantial part of work time aboard vessel)
