History
  • No items yet
midpage
Agility Public Warehousing Co. KSCP v. Mattis
852 F.3d 1370
Fed. Cir.
2017
Read the full case

Background

  • Agility contracted with DSCP (2003) to deliver food to Kuwait/Iraq; pricing split into Delivered Price + Distribution Price; Mod. 1 allowed deliveries into Iraq and said trucks "will not be used at the sites for storage purposes."
  • Mod. 2 (2003) set per-trip and per-day fees for Iraq deliveries with no cap on maximum payable days, so long truck detentions produced very large government payments.
  • Due to prolonged turnaround times and storage shortages at some Iraq sites, the government unilaterally issued Mod. 19 (2004) to add transport liaison officers (TLOs); later negotiations produced Mod. 27 (Sept. 2004).
  • Mod. 27 increased TLOs and restructured fees: established minimum trip days and a 29-day cap on payable trip days; additional days beyond minimums were payable only if delay was "customer caused" (e.g., Hub, DFAC or MKT lacking offload capability).
  • Agility accepted Mod. 27 but pressed for the ability to submit "exceptions"; DSCP/CO Ford told Agility that "exceptions to the 29 day rule will only be considered in the form of a claim." Agility submitted claims for amounts beyond the 29‑day cap; the government denied them for inadequate support and otherwise.
  • The Armed Services Board of Contract Appeals denied Agility’s appeal, holding Mod. 27 limited payment to 29 days (including storage-caused delays) and that Ford’s willingness to consider claims was discretionary; the Federal Circuit affirmed on express-breach and exceptions issues but vacated and remanded on implied-duty and constructive-change claims for further adjudication.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Did the government breach the express contract (storage prohibition in Mod. 1) by using trucks for storage and refusing to pay beyond 29 days? Mod. 1 prohibits use of trucks for storage; Mod. 27 addressed only fees and therefore did not displace the storage prohibition; government breached by using trucks as storage. Mod. 27’s plain language made governmental delays (including storage-related lack of offload) a subset of customer‑caused delays and imposed a 29‑day cap on payable days, thereby superseding Mod. 1’s residual effect. Court: Affirmed Board — Mod. 27 is unambiguous; it incorporates storage‑related delays into the customer‑caused exception and imposes the 29‑day cap, so no express breach.
Did the government promise to make exceptions to the 29‑day cap? Ford’s email ("exceptions ... will only be considered in the form of a claim") amounted to an agreement to make exceptions if Agility documented government‑caused delay. The email only promised to consider claims; it was a counteroffer and discretionary; Mod. 27 contains no binding exception language. Court: Affirmed Board — government only agreed to consider exceptions via claims; Agility cannot nullify the 29‑day cap.
Did the government breach the implied duty of good faith and fair dealing (duty to cooperate by obtaining storage, facilitating truck returns)? Even if Mod. 27 governs fee allocation, the government may have frustrated Agility’s reasonable expectations by failing to secure storage/assist returns, interfering with Agility’s performance. Government contends compliance with Mod. 27’s terms defeats any implied‑duty breach. Court: Vacated Board on this point — Board erred by not deciding the implied‑duty claim; remand to consider whether government conduct (e.g., failing to provide storage/deliberate delay) breached the implied duty and appropriate damages.
Did the government constructively change the contract by effectively using trucks as storage or otherwise altering performance requirements? Government’s conduct increased instances where Agility’s trucks were used as storage beyond contract expectations — an effective, constructive change requiring relief. Government says Mod. 27 addresses delays and fees; no constructive change. Court: Vacated Board on this point — Board failed to address the constructive‑change claim; remand required for first‑instance consideration.

Key Cases Cited

  • Forman v. United States, 329 F.3d 837 (Fed. Cir.) (review standard: contract interpretation is a question of law)
  • NVT Techs., Inc. v. United States, 370 F.3d 1153 (Fed. Cir.) (interpret contract by starting with its text and harmonizing provisions)
  • Schism v. United States, 316 F.3d 1259 (Fed. Cir.) (parol evidence rule and when extrinsic evidence is barred)
  • Centex Corp. v. United States, 395 F.3d 1283 (Fed. Cir.) (implied duty of good faith and fair dealing in government contracts)
  • Int'l Data Prods. Corp. v. United States, 492 F.3d 1317 (Fed. Cir.) (constructive change doctrine defined)
  • Bell/Heery v. United States, 739 F.3d 1324 (Fed. Cir.) (elements required to prove constructive change)
  • Metcalf Constr. Co. v. United States, 742 F.3d 984 (Fed. Cir.) (limits on using implied duty to expand express contract terms)
  • Upton v. Tribilcock, 91 U.S. 45 (U.S.) (contracting parties are bound by their contract words)
Read the full case

Case Details

Case Name: Agility Public Warehousing Co. KSCP v. Mattis
Court Name: Court of Appeals for the Federal Circuit
Date Published: Apr 4, 2017
Citation: 852 F.3d 1370
Docket Number: 2016-1265
Court Abbreviation: Fed. Cir.