History
  • No items yet
midpage
Agility Defense & Government Services, Inc. v. United States
115 Fed. Cl. 247
Fed. Cl.
2014
Read the full case

Background

  • DGS (formerly Taos) entered an IDIQ contract with the U.S. Army to procure Soviet-style weapons for Afghanistan security assistance, with firm fixed-price delivery orders and a $30,000–$50,000,000 order cap.
  • Delivery Order 6 (Dec. 7, 2007) called for 225 SPG-9s at a fixed unit price of $5,864 each, total $1,319,400, with a delivery date of April 7, 2008.
  • Hungarian and Bulgarian governments blocked weapon releases, delaying delivery; DGS did not deliver by April 7, 2008 and still hadn’t delivered by 2010.
  • On April 1, 2010, Bilateral Modification 4 waived the April 7, 2010 delivery deadline and provided 20,000 YAK-B Links as late-delivery consideration; another modification would set a new delivery date.
  • March 10, 2011 Bilateral Modification 7 allowed DGS to deliver new production SPG-9 variants, made delivery dates subject to government actions, and waived the 2-year post-original-date delivery restriction; no price increase was stated.
  • DGS delivered 225 SPG-9s on December 24, 2011; it later sought an equitable adjustment of $1,369,377.47 (April 25, 2012) for costs to acquire the new variants; the contracting officer denied the REA and final claim, leading to this litigation.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether DGS is entitled to an equitable adjustment for additional costs on a fixed-price contract. DGS argues government actions and contract modifications caused extra costs. Fixed-price contracts allocate risk to the contractor; no basis for adjustment. Denied for DGS; no equitable adjustment allowed.
Whether the Government constructively changed the contract by pressuring continued performance after April 7, 2010. DGS asserts constructive change due to government insistence. Modification 4/7, not a government-imposed change; parties agreed to new terms. No constructive change; modifications show agreement, not unilateral change.
Whether express changes (FAR 52.243-1) justified an adjustment for delivering different SPG-9 variants. Government required differing and more expensive goods. Agreement to new production SPG-9 variants was mutual, not unilateral change. Inapplicable; no unilateral change occurred.
Whether impossibility (commercial impracticability) justified an adjustment given risk of price performance. Unforeseen events rendered original price impracticable. Contract fixed-price allocates risk; market changes are ordinary risk. Not available; contractor assumed risk of higher costs.

Key Cases Cited

  • Seaboard Lumber Co. v. United States, 308 F.3d 1283 (Fed. Cir. 2002) (impossibility/practicability limitations and contractor risk under fixed-price contracts)
  • Allegheny Teledyne Inc. v. United States, 316 F.3d 1366 (Fed. Cir. 2003) (contractor bears cost risk under fixed-price contracts)
  • Dalton v. Cessna Aircraft Co., 98 F.3d 1298 (Fed. Cir. 1996) (contractor bears cost risk; impossible to adjust price under fixed-price)
  • NavCom Def. Elecs., Inc. v. England, 53 F. App’x 897 (Fed. Cir. 2002) (lack of unilateral change; when government insists on contract-compliant performance, no adjustment)
  • Int’l Data Prod. Corp. v. United States, 492 F.3d 1317 (Fed. Cir. 2007) (constructive change; equivalent to unauthorized work)
Read the full case

Case Details

Case Name: Agility Defense & Government Services, Inc. v. United States
Court Name: United States Court of Federal Claims
Date Published: Mar 19, 2014
Citation: 115 Fed. Cl. 247
Docket Number: 1:13-cv-00380
Court Abbreviation: Fed. Cl.