Acumen Re Management Corp. v. General Security National Insurance
769 F.3d 135
2d Cir.2014Background
- Acumen Re Management Corp. (Acumen) underwrote facultative reinsurance for Sorema under a 1994 Underwriting Agreement plus a 30% Contingency Commission Addendum; Sorema later became General Security.
- A 2002 Termination Agreement required General Security to pay contingent commissions for underwriting years through April 30, 2002, and to continue providing quarterly loss reports.
- General Security commuted certain certificates and recorded commutation payments as paid losses; it stopped sending quarterly reports after December 2004 and, in 2008, concluded no contingent commissions were due because Acumen’s certificates showed net losses.
- Acumen sued in 2008 for breach of contract (one count alleging five theories of breach) and breach of the implied covenant; the latter was dismissed as duplicative.
- The district court granted partial summary judgment for General Security, rejecting four of Acumen’s five breach theories and holding that, even if the remaining theory (data-quality in the contingency calculation) prevailed at trial, Acumen would be limited to nominal damages; the court certified the partial judgment under Rule 54(b) and closed the case.
- The Second Circuit held that Acumen’s five theories are a single claim (one aggregate of operative facts) and that Rule 54(b) certification was improper; the appeal was dismissed for lack of jurisdiction.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether multiple theories in one breach count constitute separate "claims" for Rule 54(b) | Acumen: the five theories are distinct, involving separate factual and legal questions that can be appealed separately | Gen. Sec.: the theories arise from one contract and a single factual core, so they form one claim | Held: single claim — the five theories are interrelated parts of one breach claim, not separate claims |
| Whether the partial summary judgment determined a claim "finally" for Rule 54(b) purposes | Acumen: district court’s ruling rejecting four theories was final and severable | Gen. Sec.: no final claim was decided because data-quality theory remained | Held: not finally adjudicated — no claim was finally determined such that interlocutory appeal is proper under Rule 54(b) |
| Whether there was "no just reason for delay" under Rule 54(b) | Acumen: certification would avoid a pointless trial on nominal damages and save resources | Gen. Sec.: Rule 54(b) prerequisites not met; closing the case doesn’t make partial judgment final | Held: court need not reach merits of this factor because first two Rule 54(b) requirements failed |
| Whether the district court’s closure of the case made the order final | Acumen: closure and Rule 54(b) entry rendered decision appealable | Gen. Sec.: clerical closure cannot convert an interlocutory ruling into a final judgment | Held: label or closure does not change substance; closure did not render order final |
Key Cases Cited
- Gottesman v. Gen. Motors Corp., 401 F.2d 510 (2d Cir. 1968) (defines a claim as the aggregate of operative facts giving rise to an enforceable right)
- Hudson River Sloop Clearwater, Inc. v. Dep’t of Navy, 891 F.2d 414 (2d Cir. 1989) (claims are separate for Rule 54(b) when based on distinct factual and legal questions)
- Backus Plywood Corp. v. Commercial Decal, Inc., 317 F.2d 339 (2d Cir. 1963) (multiple theories arising from one transaction constitute a single claim)
- Seaboard Machinery Corp. v. Seaboard Machinery Corp., 267 F.2d 178 (2d Cir. 1959) (separate counts arising from one contract are not separate claims for Rule 54(b))
- Info. Res., Inc. v. Dun & Bradstreet Corp., 294 F.3d 447 (2d Cir. 2002) (an order dismissing only part of a claim is non-final and not certifiable under Rule 54(b))
- Polansky v. Pfizer, Inc., 762 F.3d 160 (2d Cir. 2014) (label of district court judgment does not control finality; substance governs)
