History
  • No items yet
midpage
AbbVie Endocrine Inc. v. Takeda Pharmaceutical Company Limitead
CA No. 2020-0953-SG
| Del. Ch. | Sep 22, 2021
Read the full case

Background

  • AbbVie Endocrine (successor to the original distributor) and Takeda entered a requirements Supply Agreement for Lupron (leuprolide acetate); Takeda agreed to manufacture, sell, deliver, comply with laws/cGMP, fulfill firm quarterly orders, and maintain a 12-month safety stock with at least a 3-month dedicated supply for AbbVie.
  • In November 2019 FDA inspected Takeda’s Hikari manufacturing facility, issuing a Form 483, an OAI (Official Action Indicated) letter and a June 2020 Warning Letter, and later an EIR documenting multiple cGMP deficiencies; a July 2021 follow-up inspection left the site with OAI status.
  • The cGMP issues and Takeda’s remediation caused production delays beginning in 2020; Takeda produced an allocation schedule diverting scarce lots, and both parties’ safety stocks were depleted.
  • From April 2020 through at least March 2021 AbbVie placed 106 firm Lupron lots and received only 41; AbbVie alleges lost customers, doctors, market share and sales.
  • Procedural posture: bench trial (Apr–May 2021) on liability and injunctive relief (injunction denied in a separate opinion); this memorandum adjudicates breach liability and leaves damages for a later phase.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
1. Whether Takeda breached by failing to operate Hikari in compliance with cGMP (Section 16.1(a)) Takeda breached its express obligation to comply with Applicable Laws and cGMP; FDA findings show noncompliance. Takeda says best-efforts clause in Section 8.1(a) limits its obligation (i.e., only must use best efforts). Court: Specific cGMP obligation controls; FDA findings establish breach.
2. Whether Takeda breached by failing to fulfill AbbVie's firm orders (Section 9.2) Firm orders are binding and time-based; Takeda failed to deliver required quantities for quarters (106 ordered, 41 delivered). Takeda contends there is no strict timeliness requirement and only a best-efforts duty to supply. Court: Firm-order obligation is mandatory/time-based and overrides general best-efforts; Takeda breached.
3. Whether Takeda breached by failing to maintain contractually required safety stock (Section 9.6(a)) Takeda failed to keep the dedicated three-month safety stock for AbbVie beginning April 2020 (documentary evidence). Takeda argued pleading/inclusion issues and relied on allocation/shortage defenses. Court: Trial evidence shows safety-stock shortfall; breach established.
4. Whether Takeda’s use of an allocation schedule breached the contract (Sections 9.4 and force majeure 21.3) Allocation violated AbbVie’s entitlement under the agreement because shortages were within Takeda’s control. Takeda says allocation is permitted under 9.4 when it cannot supply due to causes beyond reasonable control; allocation was necessary. Court: Contract permits allocation in principle; because Takeda’s production failures were within its control, 9.4 was not triggered but using an allocation schedule was not itself a separate breach (it aggravated other breaches).

Key Cases Cited

  • Pepper Constr. Co. v. Palmolive Tower Condos., 59 N.E.3d 41 (Ill. App. Ct. 2016) (elements of a breach-of-contract claim under Illinois law)
  • Am. Fed’n of State, Cty. & Mun. Emps. v. State Labor Relations Bd., 653 N.E.2d 1357 (Ill. App. Ct. 1995) (specific contract provisions prevail over general provisions)
  • Suburban Auto Rebuilders, Inc. v. Associated Tile Dealers Warehouse, Inc., 902 N.E.2d 1178 (Ill. App. Ct. 2009) (courts construe contracts to avoid absurd results)
  • Coghlan v. Beck, 984 N.E.2d 132 (Ill. App. Ct. 2013) (principles on contract interpretation cited for breach analysis)
Read the full case

Case Details

Case Name: AbbVie Endocrine Inc. v. Takeda Pharmaceutical Company Limitead
Court Name: Court of Chancery of Delaware
Date Published: Sep 22, 2021
Docket Number: CA No. 2020-0953-SG
Court Abbreviation: Del. Ch.