History
  • No items yet
midpage
AA Construction of Missoula, LLC v. Choice Land Corp.
264 P.3d 709
Mont.
2011
Read the full case

Background

  • CLR hired Waynco as general contractor; Waynco controlled site access and subcontracting.
  • Waynco solicited and AAA submitted a bid for concrete work on March 30, 2007, totaling $94,918.25.
  • Wright signed AAA's bid with interlineations; Waynco used the bid to formulate CLR's bid and CLR accepted.
  • AAA began work May 1, 2007; Waynco authorized additional demolition for $13,500, bringing total to $108,419.25, then later sent a broader Subcontract Agreement.
  • Subcontract Agreement expanded work but did not raise compensation; AAA sent a new bid of $206,858.25 but refused to perform the added work without payment.
  • AAA left the project June 6, 2007; a construction lien was filed, substituted by a surety bond; district court awarded AAA the lien amount, costs, and later CLR sought attorney fees.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Did AAA's bid create a binding contract? AAA argues AAA's bid constituted the contract terms Waynco accepted. Waynco contends the interlineations created a counter-offer not yet accepted. Yes, AAA's bid bound the parties; acceptance occurred via performance and site control.
Did the Subcontract Agreement modify the original contract? Waynco contends oral or written modification via Subcontract Agreement. AAA contends no valid modification; assent not shown. No effective modification; no valid assent to modify the original contract.
Was Waynco the materially breaching party? AAA argues Waynco failed to pay for work performed. Waynco asserts AAA breached the contract. Waynco was the materially breaching party; AAA performed substantial work before leaving.
Is CLR entitled to attorney fees under 71-3-124, MCA? CLR seeks attorney fees as lien claimant; lien substitution doesn’t defeat its entitlement. AAA/Waynco contend lien status was altered by substitution; fee request should fail. CLR is entitled to attorney fees; lien substitution does not negate its basis.

Key Cases Cited

  • Zier v. Lewis, 352 Mont. 76, 218 P.3d 465 (2009 MT 266) (consent and mutual assent essential to contract formation)
  • Johnston v. Palmer, 337 Mont. 101, 158 P.3d 998 (2007 MT 99) (contract existence as a combined issue of fact and law)
  • Hetherington v. Ford Motor Co., 257 Mont. 395, 849 P.2d 1039 (1993) (meeting of the minds and acceptance through performance)
  • Matzinger v. Remco, Inc., 171 Mont. 383, 558 P.2d 650 (1976) (modification of written contracts by oral agreement)
  • Hutnick v. United States Fidelity & Guaranty Co., 253 Cal. Rptr. 236, 763 P.2d 1326 (1988) (bond substitution does not erode lien rights)
  • R.C. Hobbs Enterprises, LLC v. J.G.L. Distributing, Inc., 325 Mont. 277, 104 P.3d 503 (2004 MT 396) (material breach limits reciprocal actions)
Read the full case

Case Details

Case Name: AA Construction of Missoula, LLC v. Choice Land Corp.
Court Name: Montana Supreme Court
Date Published: Oct 25, 2011
Citation: 264 P.3d 709
Docket Number: DA 10-0629
Court Abbreviation: Mont.