311 P.3d 1062
Ariz. Ct. App.2013Background
- Miner contracted with the District in 2003 to build road/drainage improvements; Safeco issued a statutory performance bond for the full contract amount. Miner failed to complete the work and signed Change Order No. 2 setting July 1, 2005 as the substantial-completion date; failure to complete would be a material breach.
- Miner terminated the contract and filed suit; the District held an A.R.S. § 48-924 hearing (Miner did not appear) and the Board found Miner in default and demanded performance from Safeco.
- The District sued Miner; Safeco entered a Takeover Agreement with the District, completed the work via a subcontractor, and the District retained certain contract proceeds as estimated damages.
- The trial court granted summary judgment for the District, holding the § 48-924 default finding preclusive (res judicata), awarded both liquidated (per MAG Specs) and actual damages, and granted attorneys’ fees and costs; Miner and Safeco appealed.
- The Court of Appeals affirmed liability and the res judicata ruling as to Miner; it affirmed Safeco’s liability but vacated the liquidated-damages award against Safeco (finding ambiguity in the Takeover Agreement) and vacated the fees assessed against Safeco, remanding for further proceedings.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Preclusive effect of the §48-924 hearing (res judicata) | Miner: Board hearing was not judicial; Miner had not had a "day in court" to litigate District breach and excuse for nonperformance | District: Hearing was quasi‑judicial under §48‑924, provided notice and opportunity to be heard; Miner failed to seek special-action review, so default finding is final | Held: §48‑924 hearing was quasi‑judicial and satisfies Restatement §83 factors; Miner’s failure to appear and not seek special action bars re‑litigation of default (res judicata) |
| Recovery of both liquidated and actual damages | Miner/Safeco: Contract law bars double recovery; liquidated damages should preclude actual damages for delay | District: MAG Specs expressly provide for both liquidated delay damages and actual costs to complete; they compensate distinct harms | Held: Contract unambiguously allowed both types when for distinct injuries; actual completion costs and liquidated delay damages are separable, so both may be awarded |
| Waiver of liquidated damages under the Takeover Agreement (impact on Safeco) | Safeco: Takeover Agreement waived District’s liquidated‑damages claim against Safeco, so District may not retain liquidated damages from funds payable to Safeco | District: Waiver only limited; Agreement preserved District’s right to set off liquidated damages against any Safeco claim and did not inure to Miner | Held: Language ambiguous — could support either side; factual issue exists whether District waived liquidated damages as to retained funds; remand required as to liquidated damages against Safeco |
| Safeco’s entitlement to remaining contract proceeds / order of satisfaction | Safeco: As surety, its right to withheld contract proceeds is superior; obligee must exhaust principal’s assets first (A.R.S. §12‑1642) | District: Bond under Little Miller Act makes surety jointly and severally liable; statute and bond condition permit offsets against retained balances | Held: §12‑1642 did not control here; surety bound jointly and severally under A.R.S. §34‑222 and had no superior right to retained funds; trial court correctly denied summary judgment to Safeco on damages pending remand |
| Attorneys’ fees award | Miner/Safeco: Fees were excessive or improperly computed; Safeco also argued it did not ultimately lose to the extent claimed | District: Contractually entitled to reasonable fees as prevailing party | Held: Contractual fee provision required an award; trial court reduced requested fees and did not abuse discretion as to Miner; fee award against Safeco vacated pending remand on liquidated damages |
Key Cases Cited
- Foote v. Gerber, 85 Ariz. 366 (Ariz. 1959) (administrative board acts in quasi‑judicial manner when law authorizes hearing to determine facts and apply law)
- Pettit v. Pettit, 218 Ariz. 529 (Ariz. Ct. App. 2008) (res judicata / preclusion principles)
- Roy H. Long Realty Co. v. Vanderkolk, 26 Ariz. App. 226 (Ariz. Ct. App. 1976) (discussion of liquidated‑damages enforceability in contract context)
- Larson‑Hegstrom & Assoc., Inc. v. Jeffries, 145 Ariz. 329 (Ariz. Ct. App. 1985) (liquidated damages clause upheld against penalty challenge)
- Hartford Accident & Indemnity Co. v. Ariz. Dep’t of Transp., 172 Ariz. 564 (Ariz. 1992) (public‑contract bond and offset rights against retained contract balances)
- L & A Contracting Co. v. S. Concrete Serv., Inc., 17 F.3d 106 (5th Cir. 1994) (suretyship and material breach/default principles)
