620, Llc v. Meridian, Inc.
75331-2
| Wash. Ct. App. | Jul 17, 2017Background
- 620 LLC contracted with Meridian Construction in 2012 to build a commercial building for $986,700; after completion Meridian sought an extra $180,000 for change orders, and filed a lien.
- Meridian and 620 (through managing member Luay Joudeh) executed a written settlement agreement (Addenda D) dated June 9, 2014 resolving the lien; it required a $30,000 payment, mutual "hold each other harmless" for future claims, released Meridian from "warranty work on this building," and included a separate residential-build commitment.
- Meridian removed the lien after the settlement; 620 continued to identify construction defects and requested repairs; Meridian sent an e-mail indicating it planned certain repairs but 620 alleges Meridian never fixed them.
- 620 sued in June 2015 alleging Meridian breached the original construction contract by poor workmanship and unauthorized changes; Meridian denied liability and moved for summary judgment.
- The trial court granted summary judgment for Meridian, holding the settlement's hold-harmless clause barred 620's breach-of-contract claims; 620 appealed.
- The Court of Appeals reversed, finding genuine factual disputes about the scope and meaning of the hold-harmless provision and surrounding circumstances precluded resolution on summary judgment.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether the settlement's "hold each other harmless for any future claims on this project" provision bars 620's breach-of-contract suit | The clause was limited to resolving the lien and warranty/repair obligations; it did not release Meridian from liability for construction defects | The clause was a mutual, global release/"walk away" agreement barring any future claims related to the project, including this suit | The clause is ambiguous in context; reasonable interpretations conflict, so summary judgment is improper and the issue must go to trial |
| Whether extrinsic evidence may be considered in contract interpretation on summary judgment | 620: Extrinsic evidence (draft changes, parties' conduct, emails) shows limited scope and intent | Meridian: The plain hold-harmless language is dispositive as a global release | Court: Extrinsic evidence is admissible and demonstrates reasonable alternative meanings, so it cannot be resolved as a matter of law |
| Whether parties' post-agreement conduct (offers to repair) is consistent with a global release | 620: Meridian's offers to repair show the parties treated the settlement as limited and did not intend a full release | Meridian: Post-settlement communications are not dispositive against plain contract language | Court: Subsequent acts support 620's interpretation and create a factual issue for trial |
| Appropriateness of summary judgment on contract interpretation | 620: Single-meaning rule does not apply; multiple reasonable meanings exist | Meridian: Language is clear and judgment appropriate | Court: Because reasonable competing interpretations exist, summary judgment was improper and must be reversed |
Key Cases Cited
- Mahoney v. Shinpoch, 107 Wn.2d 679 (1987) (standard of review for summary judgment)
- Spradlin Rock Prods., Inc. v. Pub. Util. Dist. No. 1 of Grays Harbor County, 164 Wn. App. 641 (2011) (contract interpretation on summary judgment proper only if one reasonable meaning)
- Interstate Prod. Credit Ass'n v. MacHugh, 90 Wn. App. 650 (1998) (ambiguity presents factual question)
- City of Tacoma v. City of Bonney Lake, 173 Wn.2d 584 (2012) (objective is to effectuate parties' mutual intent in contract interpretation)
- Scott Galvanizing, Inc. v. Nw EnviroServices, Inc., 120 Wn.2d 573 (1993) (use of extrinsic evidence and surrounding circumstances to determine intent)
- Berg v. Hudesman, 115 Wn.2d 657 (1990) (extrinsic evidence admissible regardless of ambiguity)
- Snohomish County Pub. Transp. Benefit Area Corp. v. FirstGroup Am., Inc., 173 Wn.2d 829 (2012) (interpretation should give effect to all contract provisions)
- Kelley v. Tonda, 198 Wn. App. 303 (2017) (some disputes cannot be resolved by dispositive motion; must be tried)
