2018 Ohio 3028
Ohio Ct. App.2018Background
- AWMS applied for and eventually operated a Class II saltwater/brine injection well (AWMS No. 2) in Trumbull County; after two small seismic events (M 1.7 and M 2.1) in 2014, the ODNR Chief ordered the well shut-in pending evaluation.
- AWMS submitted a traffic-light style mitigation plan and asked to resume limited operations with monitoring; ODNR delayed, preferring to await a statewide induced-seismicity policy.
- The Oil & Gas Commission affirmed the Chief’s suspension; AWMS appealed to Franklin County Court of Common Pleas, which reversed as unreasonable and ordered a restart plan with phased limits, monitoring, and a four-person safety determination for imminent threats.
- ODNR appealed the common pleas decision to the court of appeals, arguing the trial court exceeded its authority, improperly ordered the Chief to propose plans, relied on unsupported factual findings about seismic risk, and considered evidence outside the administrative record.
- The court of appeals: (1) held the common pleas court exceeded authority only insofar as it required two commission members to act as an "imminent threat" board (no quorum power); (2) found the trial court abused its discretion by drawing unsupported factual conclusions about likely seismic risk when fashioning a restart plan; and (3) affirmed that limited reliance on a public USGS report for scientific context was harmless.
Issues
| Issue | AWMS (Plaintiff) Argument | ODNR (Defendant) Argument | Held |
|---|---|---|---|
| 1. Did the common pleas court exceed jurisdiction by ordering restart conditions and creating an oversight mechanism? | Court may craft any order the commission could have made; restart plan appropriate. | Orders intrude on Chief’s "sole and exclusive" regulatory authority and create an unauthorized "imminent threat" board. | Partially for ODNR: court lacked authority to require two commission members to act (no quorum); otherwise appellate courts may craft orders the commission/chief could have made. |
| 2. Could the common pleas court order the Chief to develop a restart plan or propose an entry? | Yes—court can direct appropriate remedial orders on appeal. | No—court improperly commanded the Chief to prepare operator plans and bypassed required technical review. | For ODNR as to compelling the Chief to propose an entry: any error was harmless; court should not force the Chief to perform tasks beyond role. |
| 3. Did the trial court abuse discretion by resolving factual questions about seismic risk and crediting AWMS experts over the Chief? | Experts supported a phased restart with monitoring; Chief’s total ban was unreasonable delay. | Trial court substituted its judgment and relied on unsupported inferences about low seismic risk. | For ODNR: trial court abused discretion by drawing likelihood conclusions about seismic risk unsupported by the record and picking experts to fashion substantive technical orders. |
| 4. Did the trial court improperly consider evidence outside the certified administrative record? | Proposed entries and public reports were proper aids; AWMS withdrew its motion to admit new evidence. | Trial court relied on materials (proposed entries, USGS report) outside the record. | For court: reliance on USGS for background was harmless; proposed entries are procedural aids and not treated as newly discovered evidence. |
Key Cases Cited
- Chesapeake Exploration, L.L.C. v. Oil & Gas Comm., 135 Ohio St.3d 204 (Ohio 2013) (statutory limits on commission authority)
- State ex rel. Morrison v. Beck Energy Corp., 143 Ohio St.3d 271 (Ohio 2015) ("sole and exclusive" authority language discussed)
- McLean v. Indus. Comm., 25 Ohio St.3d 90 (Ohio 1986) (deference to agencies with specialized expertise on statutory interpretation)
- Johnson v. Kell, 89 Ohio App.3d 623 (10th Dist. 1993) (defines "unreasonable" in administrative-review context)
- Citizens Comm. to Reserve Lake Logan v. Williams, 56 Ohio App.2d 61 (10th Dist. 1977) (factual foundation required to avoid "unreasonable" determination)
